Inquiry:

1. In regards to contract # 02A2380; on sheet DQ-1 Hot Mix Asphalt (type A) the unit is listed as ''ton'', but on the price quote proposal item number 11 Hot Mix Asphalt (type A) the unit is listed as CY. Please clarify.

2. Just reaching out regarding this minor B project bidding on Thursday. Bid item 11 on the proposal sheet uses cubic yards for a unit of measurement while the plans show that quantity in tons. Please clarify which unit of measurement is to be used on the proposal sheet.

Response:

1. The correct unit of measure is “TON”. Please refer to addendum 1, dated 02/19/2025.

2. The correct  unit of measure is “TON”. Please refer to addendum 1, dated 02/19/2025.