North Region Construction Project 02A2485
Forest Route Culverts
Contract
02A2485 Minor B
02-1K780
Bid Date
02/10/2026
County Route
TRI-036
Description
Drainage Restoration
Bidder Inquiry / Response
Inquiry:
- When is the expected start date of this project? This Winter?
- Can retarders be added to concrete mix design since it is over 1.5hr haul to site?
- When was the estimate for this job calculated?
- Will a AFAD be necessary if the job is planned to be flagged the whole time?
Response:
- When is the expected start date of this project? This Winter?
To be determined after contract execution.
- Can retarders be added to concrete mix design since it is over 1.5hr haul to site?
- Bid per standard and project specifications.
- When was the estimate for this job calculated?
Fall 2025
- Will a AFAD be necessary if the job is planned to be flagged the whole time?
Bid per bid item list and specifications.