Auburn - Caltrans is alerting motorists that construction has paused on the $12.3 million American Canyon Roundabout Project in Auburn, at the intersection of State Route 49 (SR-49) and Lincoln Way/Borland Avenue, due to unforeseen permit issues.
The delay comes after a second long-term closure of Borland Avenue where work was performed to construct portions of the roundabout. During that time, crews continued working with the intention to finish the roadway along Borland Avenue after obtaining permits necessary to complete the work.
These permits are necessary to complete the utility work before the remainder of the project moves forward. The duration of the delay is unknown, but construction is anticipated to resume by late fall.
So far, crews have constructed the embankment for the new highway alignment along with the installation of new culverts and inlets. Sidewalk improvements have started at the southwest and northwest corners of the intersection.