Placer County – Caltrans is alerting area residents about the start of paving work on the Interstate 80 (I-80) off- and on-ramps at Drum Forebay and upcoming overnight closures of the mainline at the Cisco Grove and Baxter overcrossings in Placer County.
Beginning the week of August 8, construction crews will start grinding work on the Drum Forebay ramps to remove the top layer of asphalt concrete. While the ramps are expected to remain open, motorists may experience intermittent traffic control and short closures for construction activities. Following the grinding work, motorists should expect slight concrete grade differences and a coarse roadway texture prior to final paving work near the end of August.
In addition, I-80 motorists should expect full nightly interstate closures between 8 p.m. and 8 a.m. Monday, August 8 through Thursday, August 11 for placement of new concrete girders for the Cisco Grove overcrossing. During girder installation all passenger and commercial vehicles will be detoured off the interstate at the off-ramps and back on via the on-ramps. A mainline interstate closure is also scheduled between 8 p.m. and 8 a.m. Tuesday, August 23 and Wednesday, August 24 for girder placement at the Baxter overcrossing. The same ramp detours will be utilized with minor travel delays expected.
The work is part of a $57 million project to replace four I-80 bridge overcrossings in Placer County: Crystal Springs, Baxter, Drum Forebay and Cisco Grove. The structures are being demolished and rebuilt due to cracking and spalling of the concrete decks and high corrosive chloride content in the deck surfaces. All overcrossings are being widened to include 8-foot shoulders, 6-foot sidewalks and will include ramps that comply with Americans with Disabilities Act (ADA) standards.
The project includes $3.48 million in funding from Senate Bill 1, the Road Repair and Accountability Act of 2017. SB 1 provides $5 billion in transportation funding annually split between the state and local agencies. Road projects progress through construction phases more quickly based on the availability of SB 1 funds, including projects that are partially funded by SB 1. For more information about other transportation projects funded by SB 1, visit Rebuilding California.
Project construction began in April 2021 with completion expected in summer 2023. Walsh Construction of Concord is the prime contractor.
The department will issue construction updates on Twitter @CaltransDist3, on Facebook at CaltransDistrict3 and on the Caltrans District 3 website. For real-time traffic, click on Caltrans' Quickmap or download the QuickMap app from the App Store or Google Play.
###