FixSac5 Weekend Work Completed Ahead of Schedule (07/20/2020)

Published:

Interstate 5

District:  District 3 - Marysville
Contact:  Angela DaPrato
Phone:  (916) 826-3093

 

FOR IMMEDIATE RELEASE

Sacramento County — The California Department of Transportation (Caltrans), Norcal Paving a joint venture of A. Teichert and Son Inc. and Granite Construction Companies completed this weekend’s work for the Interstate 5 Corridor Enhancement (FixSac5) Project ahead of schedule.

The extended weekend closure began at 9:00 p.m. July 17 and was scheduled to end at 5:00 a.m. July 20, however, crews were able to reopen the northbound lanes on July 19 at 8:00 p.m. (nine hours early) and the southbound lanes on July 19 at 9:00 p.m. (eight hours early). All ramps between Florin Road and Seamas Avenue were also reopened ahead of schedule.

Crews closed the northbound lanes from Florin Road to Seamas Avenue, and southbound lanes from Sutterville Road to Florin Road for roadway excavation, removing concrete, subgrade work, paving, striping and other construction activities. Two lanes remained opened in each direction while crews worked around the clock.

Although the scheduled work for this weekend’s extended closure finished early, crews are still working on the SAC 5 Corridor Enhancement (FixSac5) Project and motorists should expect ramp and lane closures this week from 8:00 p.m. to 7:00 a.m. Monday through Friday. Motorists expect delays and use State Route 99 as an alternate route. For more information about this week’s work schedule visit the District 3 Roadwork Page or FixSac5. Caltrans encourages the public to follow @CaltransDist3 and @FixSac5, and for more information about the project text ‘FixSac5’ to 58632.

The California Highway Patrol (CHP) will be patrolling the project site ticketing motorists who are not adhering to the posted speed limit signs. The speed limit has been reduced to 55 MPH through the construction zone 24/7. The closures and speed limit reductions are necessary for the safety of motorists and workers. Caltrans advices motorists to “Be Work Zone Alert” – someone’s loved one is at work.

The sixth extended closure scheduled for the weekend of July 24 has been postponed. Crews are scheduled to resume the extended closures in August.

The $370 million SAC 5 Corridor Enhancement Project extends from about one mile south of Elk Grove Boulevard Overcrossing to the American River Bridge, and will rehabilitate pavement, construct new High Occupancy Vehicle (HOV) lanes, replace a pedestrian overcrossing, construct sound walls, install new fiber optic lines, new ramp meters and extend various entrance and exit ramps. Funding includes $48.3 million from SB 1. Although nighttime work is scheduled for most of the work, there is major traffic interfering work that will include 16 extended-weekend and daytime closures. The contract was awarded May 31, 2019 to Norcal Paving a joint venture of A. Teichert and Son Inc. and Granite Construction Companies, and construction began in late July 2019. The project is expected to be completed by December 2022.

Work is scheduled to begin as listed but subject to change due to traffic incidents, weather, availability of equipment and/ or materials, and construction related issues.

Check out Caltrans’ “Caltrans QuickMap” for current road conditions or download the free QuickMap app on the App Store or Google Play. Motorists also can call the California Highway Information Network automated phone service at 1-800-427-ROAD (7623).

 

#

 