Shasta 5 Wrong Way Ramps Project on Interstate 5 in Shasta County

The Project:
The Shasta 5 Wrong Way Ramps Project will upgrade or install signage and apply enhanced pavement markings at all exit ramps on Interstate 5 from just south of Gas Point Road to just north of Railroad Park Road.
Project Includes:
Upgrading or installing signage and applying enhanced pavement markings at all exit ramps on Interstate 5 between the Tehama/Shasta County line and the Shasta/Siskiyou County line
Current Project Schedule:
There are an estimated 60 working days for the project, all of which will require traffic control. Construction is anticipated for 2026.
Receive Updates:
Follow Caltrans District 2 on Facebook and Twitter (X).
Contacts:
Project Manager: Brandon Trent
Public Information Officer: Chris Woodward