I-5 / El Toro Road Interchange Improvement Project

 To view additional project information, please view Orange County Transportation Authority (OCTA) website here.

Introduction

The California Department of Transportation (Caltrans), in partnership with the Orange County Transportation Authority (OCTA), proposes to modify and improve the existing Interstate 5 (I-5)/El Toro Road Interchange between post miles (PM) 17.8 and 19.7, located within the cities of Lake Forest, Laguna Woods, and Laguna Hills in Orange County, California (see Figure 1, Project Location Map). Caltrans, as assigned by the Federal Highway Administration (FHWA), is the Lead Agency under the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA).

The purpose of the I-5/El Toro Road Interchange Project (Project) is to improve traffic flow, optimize traffic signalization, improve traffic mobility at and through adjacent local street intersections, reduce freeway ramp queuing, and apply technology to help manage traffic demand. The proposed alternatives are: Build Alternative 1 (Southbound I-5 Hook Ramps), Build Alternative 1a (Design Variation), Build Alternative 3 (TSM/TDM), and the No-Build Alternative.

 

 Map displaying project vicinity along I-5 within Orange County in CaliforniaMap displaying project limits along I-5 near El Toro Road

  

 

Project Status: Environmental Phase

Caltrans is the lead agency under the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA). Caltrans is preparing a Final Environmental Document (FED) pursuant to CEQA and NEPA guidelines. The Project is currently in the environmental phase. The Draft Environmental Document (DED) was completed in July 2026, and the FED is anticipated for approval in early 2027. Read more about the environmental study process below.

Environmental Study Process

The environmental study process is an important and mandatory part of project development. This multi-year process includes technical studies and opportunities for public participation and comment, including before and during the DED review phase. It must comply with NEPA and CEQA, as well as any other applicable federal and state laws. Accordingly, Caltrans must analyze potential project alternatives and inform decision-makers and the public about potential environmental impacts.

As part of this process, Caltrans analyzed effects on physical, biological, and human environments. If it is determined that the proposed project may have potentially significant impacts, then measures to avoid, minimize, and/or mitigate those impacts must be considered and implemented. Click here more information on NEPA. Click here for more information on CEQA.

The Project’s environmental review phase began with public scoping in 2023. The purpose of public scoping meetings was to provide information to agencies and the public regarding the proposed project and to obtain feedback on the scope and content that should be addressed in the environmental document. An initial public scoping period was held for a 33-day period between July 11 and August 25, 2023. In response to public comments received during the initial scoping period, Caltrans extended the public scoping period by 45 days, from November 1, 2023, to December 18, 2023. 

An in-person scoping meeting was held at the Lake Forest Community Center on Wednesday, July 26, 2023, from 4:00 p.m. to 7:00 p.m. A virtual scoping meeting was held on August 3, 2023 on Zoom. Please see documents from the scoping meetings linked below under Available Resources. The scoping meetings offered the public an opportunity to provide comments during the scoping phase for the I-5 Interstate 5 (I-5)/El Toro Road Interchange Project. Formal public comments were accepted during the scoping period and were documented and reviewed by the Project team. 

Following scoping, technical studies were completed. A DED was prepared that included the findings of the environmental studies. The public circulation period for the DED is from July 31 to September 14, 2026. The approval of a FED is anticipated in early 2027.

One No Build Alternative and two Build Alternatives (including one design variation), ranging from $29 million to $333 million for the proposed build alternatives, were studied:

  • Alternative No. 1 (Southbound I-5 Hook Ramps)
    • Alternative No. 1a (Design Variation)
  • Alternative No. 3 (TSM/TDM)
  • No-Build Alternative

Draft Environmental Document

The Draft Environmental Impact Report/Environmental Assessment will be made available to the public and circulated to regional and local agencies to provide opportunity for their comments from July 31st to September 14th, 2026.

The document will be available for review below on this website and at the following locations:

  • Caltrans District 12 Office, 1750 East 4th Street, Suite 100, Santa Ana, CA 92705 (8am-5pm Monday-Friday)
  • Laguna Woods Library, 24264 El Toro Road, Laguna Woods, CA 92637 (9am-5pm Monday-Friday)
  • El Toro Library, 24672 Raymond Way, Lake Forest, CA 92630 (10am-7pm Monday-Thursday) ; (9am-5pm Friday & Saturday)
  • Laguna Hills Library, 25555 Alicia Parkway, Laguna Hills, CA 92653 (10am-7pm Monday-Thursday) ; (9am-5pm Saturday)

Comments may be submitted during the public circulation period (July 31, 2026 – September 14, 2026) in any of the following formats:

  • Mail to Caltrans District 12: Div. of Environmental Analysis, 1750 East Fourth Street, Suite 100, Santa Ana, CA 92705
  • Email comments to D12.ELToro@dot.ca.gov with the subject line “I-5 El Toro Road Interchange Project”.
  • Provide comments in writing or with a court reporter at the upcoming public hearings.

Upcoming Public Hearing

  • The in-person public hearing will be held on Wednesday, August 26 from 5:00 pm to 7:00 pm at the Laguna Hills Community Center in Laguna Hills, CA.
  • The virtual public hearing will be held on Zoom on Wednesday, September 2 from 5:00 pm to 7:00 pm. Register at bit.ly/ETRopenhouse.

Next Steps

  • Early 2027 - Final Project Report and Final Environmental Document
  • May 2027 - Begin Design Phase
  • Late 2029 – Completion of Project Design
  • Early 2032 - Begin Construction
  • 2035 – Opening Year 

Project Milestones

Milestone
Timeline

Project Initiation

Caltrans initiates the development of the proposed project

Early 2013

Public Scoping Meetings

Summer 2023

Technical Studies & Draft Environmental Document

Technical experts conducted preliminary engineering and technical studies for the DED.

2023 – 2026

Public Hearing and Circulate Draft Environmental Document

Technical studies were compiled into the DED and made available for public review and comment during a 45-day circulation period. During circulation two public hearings are held with informational exhibits on display and the project team available to respond to questions. The public was provided the opportunity to provide written and verbal comments.

August - September 2026

Identify/recommend preferred alternative

The project development team identifies and recommends a preferred build alternative based on the result of the technical studies and public comment. Caltrans is responsible for the final approval of the preferred build alternative and FED.

Fall 2026

Approve Build Alternative Final Environmental Document

The FED will include identification of the recommended preferred alternative and final approval by Caltrans. Response to comments received during the circulation period will be included in the FED. Caltrans will give notice of the FED availability and provide the public opportunity to review.

Early 2027

Available Resources

Accessibility Assistance: Caltrans makes every attempt to ensure our documents are accessible. Due to variances between assistive technologies, there may be portions of this document which are not accessible. Where documents cannot be made accessible, we are committed to providing alternative access to the content. Should you need additional assistance, please contact the Caltrans District 12 Public Information Office at (657) 328-6000 or visit https://dot.ca.gov/request-ada-compliant-documents.

Draft Environmental Document (DED)

DED Studies and Report

The technical studies and reports are available as indicated below during the public circulation period.

  • Geotechnical Review Memorandum of District Preliminary Geotechnical Report (January 2025) (upon request via project email)
  • Jurisdictional Delineation Report (April 2025) (upon request via project email)
  • Floodplain Evaluation Report/Location Hydraulic Study (May 2025) (upon request via project email)
  • Natural Environment Study – Minimal Impacts (April 2025) (upon request via project email)
  • Phase I Initial Site Assessment (January 2025) (upon request via project email)
  • Structures Preliminary Geotechnical Report (February 2025) (upon request via project email)
  • Supplemental Air Quality Report (December 2025) (upon request via project email)
  • Supplemental Archaeological Survey Report (December 2025) (upon request via project email)
  • Supplemental Community Impact Assessment (July 2026)
  • Supplemental Draft Relocation Impact Report (June 2026) (upon request via project email)
  • Supplemental Energy Analysis Report (December 2025) (upon request via project email)
  • Supplemental Historic Property Survey Report (December 2025) (upon request via project email)
  • Supplemental Historical Resources Evaluation Report (December 2025) (upon request via project email)
  • Supplemental Noise Abatement Decision Report (July 2026)
  • Supplemental Noise Study Report (January 2025)
  • Supplemental Paleontological Identification Report/Paleontological Evaluation Report (July 2025) (upon request via project email)
  • Supplemental Relocation Impact Report (upon request via project email)
  • Supplemental Visual Impact Assessment (July 2026)
  • Traffic Operations Analysis Report (May 2026)
  • Vehicle Miles Travelled Assessment (May 2024) (upon request via project email)
  • Water Quality Assessment Report (March 2025) (upon request via project email)

Other Resources

Public Hearing Materials

  • Fact Sheet (to be posted)
  • Frequently Asked Questions (to be posted)

Public Scoping Meeting Materials

The following materials are available on OCTA's website and are linked below:

Get Involved and Stay Connected

Sign up through our external project website to receive project information and alerts.

Follow Caltrans District 12 on X, Facebook, and/or Instagram.

Use Quickmap for real time traffic updates. Quickmap can be accessed online or downloaded from the App Store or Google Play Store.

Project Email:

D12.ELToro@dot.ca.gov