Rest Area & Lane/Ramp Closures
Interstate 5 And State Routes 59, 99, 140 & 165
Merced County – The California Department of Transportation (Caltrans) will perform various closures on Inte6rstate 5 (I-5), and State Route 59 (SR-59), SR-99, SR-140 and SR-165 for maintenance and construction operations. Work is scheduled to occur as follows:
Interstate 5
- Full closure of the John C. Erreca Rest Areas on northbound and southbound I-5 beginning Monday, April 4, 2022, through July 31, 2025.
- ALTERNATE LOCATIONS: Motorists are advised to use the Coalinga-Avenal Rest Area (Fresno/Kings County line).
State Route 59
- Long-term lane/shoulder closures northbound and southbound 16th Street Bridge for bridge work beginning Monday, February 10 at 8:00 p.m. through Wednesday, December 31, 2025, at 11:00 p.m.
State Route 99
- Full off-ramp closure southbound SR-99 at South Avenue Over-Crossing for landscape/irrigation work on Tuesday, July 29, 2025, from 9:00 a.m. until 1:00 p.m.
- Full on-ramp closure southbound SR-99 at South Avenue Over-Crossing for landscape/irrigation work on Wednesday, July 30, 2025, from 9:00 a.m. until 1:00 p.m.
- Alternating lane closures northbound SR-99 from Bert Crane Road to the Merced/Stanislaus County Line for sweeping work beginning Monday, July 28, 2025, through Tuesday, July 29, 2025, from 8:00 a.m. until 3:00 p.m.
- Alternating lane closures southbound SR-99 from the Merced/Stanislaus County Line to the West Atwater Over-Head for sweeping work beginning Wednesday, July 30, 2025, through Thursday, July 31, 2025, from 8:00 a.m. until 3:00 p.m.
State Route 140
- One-way traffic control from South Avenue to Sixth Avenue/Fourth Street for utility work beginning Monday, July 28, 2025, through Friday, August 1, 2025, from 9:00 a.m. until 3:00 p.m.
State Route 165
- One-way traffic control from Mercy Springs Road Over-Crossing to California Aqueduct Bridge for highway construction work beginning Tuesday, July 29, 2025, through Wednesday, July 30, 2025, from 10:00 p.m. until 6:00 a.m.
- One-way traffic control at Greer Avenue for utility work beginning Tuesday, July 29, 2025, through Wednesday, July 30, 2025, from 8:00 p.m. until 6:00 a.m.