Inquiry #1: 08-1C4304

On page 12 of the specials in Section 39 Hot Mix Asphalt under “Replace section 39-1.12E of the RSS for section 39-1.12 with:”
The contractor is directed to profilograph the existing roadway, determine must-grind areas and complete must-grinds prior to repaving.

There are no provisions stated for measurement or payment of this work.

Please provide a bid item for Prepaving Profilograph (390010) and another bid item for Prepaving Grinding Day (390020).

Unless Caltrans adds these items it will be impossible for the contractor to quantify and bid this work correctly.

Inquiry submitted 04/17/2013

Response #1:Submitted for consideration.
Response posted 04/19/2013


Response #2:An Addendum will be forthcoming to address this Inquiry.
Response posted 04/25/2013




Inquiry #2:
Upon finishing the site visit on this project it has come to our attention that there is an existing centerline rumble strip from PM 80.3 to 92.3. Is it Caltrans intent for the contractor to pave over the existing rumble strip without first milling it out and replacing the milled out section? Also there is no direction in the bid documents to replace the rumble strip. Please advise.


Inquiry submitted 04/19/2013

Response #1:Submitted for consideration.
Response posted 04/19/2013


Response #2:An Addendum will be forthcoming to address this Inquiry.
Response posted 04/25/2013




Inquiry #3: On Page 7 of the Special Provisions, it shows reversible control only allowed at night from 7 pm to 5 am. Is it the States intention for this project to be night work?
Inquiry submitted 04/19/2013

Response #1:Submitted for consideration.
Response posted 04/19/2013


Response #2:Yes, TMP and LRC shows this project is to be night work.
Response posted 04/23/2013




Inquiry #4: What exactly are we preparing the lead compliance plan to address? There does not appear to be any yellow thermoplastic striping in the project limits, nor are there are any striping removals, only markers.
Inquiry submitted 04/29/2013

Response #1:Submitted for consideration.
Response posted 04/30/2013


Response #2:Lead Compliance is for Pavement Markers.
Response posted 04/30/2013




Inquiry #5: What is the lead plan being prepared for?
There is no existing yellow thermoplastic on the job

Inquiry submitted 04/30/2013

Response #1:Please refer to Inquiry # 4.
Response posted 04/30/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.