Inquiry #1: This project bid back on 3/8/2012 and had 400 tons of slurry seal with 35 working days. Now the project is re-bidding with 8,410 tons of slurry seal with the same 35 working days. My question is, does Caltrans plan on adjusting the working ways to reflect the revised quantity of slurry seal ?

Inquiry submitted 03/05/2013

Response #1:Submitted for consideration
Response posted 03/05/2013


Response #2:The working days were based on similar projects constructed . The calculation was a correction and did not affect the working days as the limits of work and scope did not change.
Response posted 03/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.