Inquiry #1: Ref Special Provision, page 9 Section 9 Payment for items not incorporated into the Work- Can all other guard rail and terminal systems, that are provided for on Contracts 08-0K2504 and 08-0K2604 be added to this project for items not incorporated into the Work?
Inquiry submitted 10/30/2012

Response #1:Submitted for consideration
Response posted 10/31/2012




Inquiry #2: Ref Item 37- Please provide clarification via an addendum to all plan holders of your requirements. Following are omissions and inconsistancies of the current contract documents, for this work:-
1- Is this to be a Final(F) pay quantity as usual.

2-Dimensions given on detail plan sheet C-2 and C-3, do not calculate to the quantity per each shown on sheets 23 and 24.

3-Ref Plan Sheet 6 (C-3) Please provide details for the individual Type 9, Alternatives required for locations called out as "Type 9" on Quantity Sheets 23 and 24.

Inquiry submitted 10/30/2012

Response #1:Submitted for consideration
Response posted 10/31/2012


Response #2:1. This is not a Final (F) pay item on this contract.
2. On construction details, it is stated that 3'-6" is the minimum. The concrete calculations used assumed a longer length of 4'-5".
3. Alternatives for type 9 will be determined in the field.
Response posted 10/31/2012




Inquiry #3: This project bids 1 week later than project 08-0K2604 and ties directly onto that project. Will contract time run concurrently with the other project or will it be delayed so that traffic disruptions are limited to one project at a time.
Inquiry submitted 10/31/2012

Response #1:Submitted for consideration
Response posted 10/31/2012


Response #2:Both projects will run concurrently.
Response posted 10/31/2012




Inquiry #4: For rubber plants the Material Plant Quality Program is set to go into effect on July 1, 2013. Does this program apply to this project.
Inquiry submitted 11/13/2012

Response #1:Submitted for consideration
Response posted 11/13/2012


Response #2:This program does not apply to this project.
Response posted 11/14/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.