Viewing inquiries for 04-3S7524

Submit new inquiry for this project


Inquiry #1: This being a short term job 45 working days,could portable traffic signals,light towers for illumination and solar flashing beacons all seperate bid items be used instead of specified temporary signal system.The state would save money and if this was Emergency, Informal Project through construction this would be there method.
Inquiry submitted 05/20/2013

Response #1:Submitted for consideration.
Response posted 05/21/2013


Response #2:Portable Traffic Signal is not allowed. Please bid this item per the contract.
Response posted 05/21/2013




Inquiry #2: The bid item list for this project does not contain an item for Mobilization or Clearing & Grubbing. How are these items of work to be paid?
Inquiry submitted 06/06/2013

Response #1:Submitted for consideration.
Response posted 06/07/2013


Response #2:This project does not contain Mobilization and Clearing & Grubbing items, both of these items are considered to be included in the prices paid for the various other items.
Response posted 06/10/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.