Viewing inquiries for 04-3E5104

Submit new inquiry for this project


Inquiry #1: Q1) Do we have to clean joints after removal of old neoprene strip seals and before installation of new strip seals? If they require cleaning, is it paid for within Bid Item #37, Replace Neoprene Gland?


Q2) Locations 1, 2, 7, and 10 require joint reconstruction at the abutments. Are joints reconstructed at both abutments at each location? A quantity takeoff for structural concrete (bridge) at both abutments is about twice the bid quantity, which leads me to believe only one abutment at each location is rebuilt. This is a (F)inal Pay Item. Please advise limits of joint reconstruction.

Inquiry submitted 05/13/2014

Response #1:Submitted for consideration.
Response posted 05/14/2014


Response #2:1. The joints must be cleaned prior to installation of new joint seal. Cleaning the joint is a separate bid item.

2. For locations 1, 2, 7, and 10 the concrete quantities to reconstruct the joints are included for both abutments at each location as shown on plan.

Response posted 05/14/2014






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.