SAN DIEGO — Caltrans added nearly 1,200 lane miles of pavement repair and 66 bridges to its growing list of projects to be delivered sooner than planned thanks to the imminent influx of revenue from the Road Repair and Accountability Act of 2017 (SB 1), the transportation funding and reform package passed in April. To date, Caltrans has now expedited nearly $5 billion in "fix-it-first" projects since the spring.

"Years of unfunded maintenance needs have plagued our roadways, so Caltrans is expediting projects with the expectation of SB 1 funds coming in November. We are lining up projects that are going to deliver real results for all users of the state transportation system."

Malcolm Dougherty, Director, Caltrans

This latest approval of 90 major "fix-it-first" transportation projects, worth nearly $3.4 billion, are part of a list Caltrans submitted to the California Transportation Commission (CTC) that was voted on at the Commission's October meeting.

Improvements to be made by these projects include:

  • improving or replacing 66 bridges
  • rehabilitating nearly 1,200 lane miles of pavement on highways across the state
  • repairing more than 300 culverts and drainage systems
  • and installing nearly 2,400 elements that are part of traffic management systems that help manage traffic and reduce congestion.

Among the projects that received funding allocations were:

District 11 CTC Funding Allocations October 2017

  • A $15.2 million pavement improvement project on State Route 52 from State Route 163 to east of Santo Road.
  • A $3.75 million curve realignment and shoulder widening project on State Route 94 in the community of Dulzura near Marron Valley Road.
  • A $18.36 million Interstate 805 (I-805) Sweetwater River Bridge Upgrade Project.
  • A $4.58 million project to replace 25 Changeable Message Signs in San Diego County.
  • A $8.12 million pavement improvement project on I-805 from Mira Mesa Boulevard to the end of the freeway.
  • A $3 million project on Interstate 5 at the San Ysidro Port of Entry to place high friction surface treatment.
  • A $9.36 million culvert rehabilitation project on I-5 from Lomas Santa Fe to just south of Tamarack Avenue.

The projects authorized today come on the heels of more than $285 million in accelerated existing highway repair projects announced earlier in July, and nearly $901 million in "fix-it-first" projects in August.

SB 1 provides an ongoing funding increase of approximately $1.8 billion annually for the maintenance and rehabilitation of the state highway system, including $400 million specifically for bridges and culverts. SB 1 funds will enable Caltrans to fix more than 17,000 lane miles of pavement, 500 bridges and 55,000 culverts by 2027. Caltrans will also fix 7,700 traffic operating systems, like ramp meters, traffic cameras and electric highway message boards that help reduce highway congestion.