I-5-Full Freeway Closure

Published:

i5 North enhancement project

Weldon Canyon Rd Bridge Demolition (METRO) Summary

As part of the I-5 North County Enhancements Project, Metro’s contractor OHLA-USA, will be removing the existing Weldon Canyon Rd Bridge as the new one will be ready for use in late August. Activities will include the removal and demolition of the existing Weldon Canyon Rd bridge superstructure and columns, requiring a full freeway closure will take place from SR-14 to Calgrove Bl starting Saturday, November 4, 2023 at 8pm to

Sunday, November 5, 2023 at 8amAdditional closures will take place as a contingency on December 2, 2023 from 8pm to 8am, if needed

 

What to Expect/Traffic Control

Northbound full directional closure between SR-14 and Calgrove Bl, anticipated on Saturday, November 4, 2023 at 8pm to Sunday, November 5, 2023 at 8am

  • Primary detour and truck route: Exit I-5 to northbound SR-14, continue to westbound Golden Valley Rd/Newhall Ranch Rd, proceed to the Newhall Ranch Rd I-5 on-ramps.
  • Local detour route: Exit I-5 to northbound SR-14, continue to westbound Newhall Av, right on Railroad Av, left on Lyons Av, proceed to the Lyons Av/Pico Canyon Rd I-5 on-ramps.

Southbound full directional closure between Calgrove Bl and SR-14, anticipated on Saturday, November 4, 2023 at 8pm to Sunday, November 5, 2023 at 8am

  • Primary detour and truck route: Exit I-5 to eastbound Newhall Ranch Rd/Golden Valley Rd, continue to southbound SR-14 off of Golden Valley Rd, proceed to the SR-14/I-5 interchange.
  • Local detour route: Exit I-5 at Calgrove Bl, continue south on The Old Road, south on San Fernando Rd and Sepulveda Bl, proceed to I-5 southbound on-ramp.

 

Closure Detour Maps

Primary Detour Truck Detour