Statewide Summary
$3.5 Billion and 294 Projects
Ready to List (RTL) Milestone Delivery
Description
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
Total
Number of Planned Deliveries
42
54
98
47
241
Number of Advanced Deliveries
4
13
20
16
53
Construction Value
($ Millions)
$376.2
$882.4
$1,073.2
$1,208.2
$3,539.9