Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 4 3 8 3 18
Number of Advanced Deliveries 0 0 0 1 1
Construction Value
($ Millions)
$33.4 $55.9 $31.4 $194.1 $314.8

District 8 commits to the deliveries by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Michael A. Perovich, District 8 Director, 7/27/07

Signed by, Will Kempton, Director, on 7/27/07

Attachment: 2007/2008 FY Project RTL Baseline Delivery Plan