District 6
Contract for Delivery
FY 2007/2008

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 5 5 5 2 17
Number of Advanced Deliveries 1 1 1 2 5
Construction Value
($ Millions)
$18.3 $24.0 $22.8 $57.2 $122.4

District 6 commits to the deliveries by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Malcolm X. Dougherty, District 6 Director, on 7/27/07

Signed by, Will Kempton, Director, on 7/27/07

Attachment: 2007/2008 FY Project RTL Baseline Delivery Plan