Restoring the Golden State

Statewide Summary
Contract for Delivery
FY 2006/2007

$2.3 Billion and 286 Projects

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 76 46 57 46 225
Number of Advanced Deliveries 4 11 19 27 61
Construction Value
($ Millions)
$414.2 $473.8 $552.3 $872.8 $2313.1