Restoring the Golden State

District 7
Contract for Delivery
FY 2006/2007

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 9 4 4 14 31
Number of Advanced Deliveries 0 1 3 10 14
Construction Value
($ Millions)
$183.7 $61.5 $13.9 $201.7 $460.8

District 7 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Doug Failing, District 7 Director, on 6/22/06

Signed by, Will Kempton, Director, on 6/22/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan