Contract for Delivery
FY 2006/2007

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 10 3 9 1 23
Number of Advanced Deliveries 1 0 5 0 6
Construction Value
($ Millions)
$35.7 $8.9 $45.1 $0.5 $90.1

District 6 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Malcolm Dougherty, District 6 Director, on 8/15/06

Signed by, Will Kempton, Director, on 8/15/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan