PART 3: Identify Project Need And Project Initiation Document

 

I. Identify Project Need

A.   Project Initiation and Planning (100.05.05)

Initiation

II. Project Initiation Document

A.   Define Transportation Need and Assess Site (150.05)

Obtain and Review Existing Reports, Studies and Mapping (150.05.05) --- Tasks P08 - P26 ---
Define Problem (150.05.35)--- Task P27 ----
Identify Environmental Constraints (150.05.20) --- Task P28 ---

B.   Develop Initial Alternatives ( WBS 150.10)

Develop Concept Alternatives (WBS 150.05.15 - Early Tasks)--- Tasks P29 - P30 ---
Obtain Public Input (WBS 150.10.05)--- Task P31 ---
Perform Value Analysis (WBS 150.10.10)--- Task P32 ---
Develop Concept Alternatives (WBS 150.10.15)--- Tasks P33 - P59 ---

C.   Draft Agreements ( WBS 205.)

Obtain Freeway Agreement (WBS 205.20) --- Task P60 ---
Obtain Maintenance Agreement (WBS 205.20)--- Task P61 ---
Preliminary Cooperative Agreement (WBS 205.35)--- Task P62 ---

D.   Analyze Alternatives (WBS 150.15)

Prepare R/W Data Sheets (WBS 150.15.05)--- Tasks P63 - P64 ---
Assess Utility Relocation Requirements (WBS 150.15.10)--- Task P65 ---
Determine Railroad Involvement (WBS 150.15.15)--- Task P66 ---
Prepare and Obtain Approval for Design Exceptions (WBS 150.25.10)--- Tasks P67 - P68 ---
Develop Cost Estimates (WBS 150.15.55)--- Tasks P69 - P72---

E.   Prepare and Approve PID (WBS 150.25)

Prepare Draft PID (WBS 150.25.05)--- Tasks P73 - P75 ---
Prepare Storm Water Data Report (WBS 150.25.25)--- Task P76 ---
Circulate, Review and Approve PID (WBS 150.25.20)--- Tasks P77 - P89 ---

Return to Table of Contents