California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 600

Complete Construction Project

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Task (D437) 

Milestone
Task Group
 
 Last Update

D437
Prepare Final Construction Project Records

(600.A)

11/28/94


TASK D437 (600.A)

Prepare Final Construction Project Records

Narrative

This is a construction activity; however, it is included in the Project Development Workflow Tasks to show project completion.

Initiator

Sub-Tasks

Task Duration

References