California State Department of Transportation
Project Development Workflow Tasks (PDWT)
|
PYPSCAN Milestone 500
Approve Contract
(Click on highlighted Task to see detailed information.)
TASK D435 (500.A)
Request Preparation of Maintenance Agreements
and Relinquishment Maps
Narrative
Relinquishment limits and maintenance responsibilities need to be reviewed
prior to relinquishing constructed facilities.
Initiator
Sub-Tasks
- After award of the contract, request the Right of Way Engineering Unit
to prepare maps showing limits of relinquishments. The Right of Way Engineering
Unit sends the plans to the Project Engineer and the Maintenance Unit.
- Review features such as:
- City limits
- Permanent drainage or slope easements
- Maintenance Unit prepares final Maintenance Agreements, identifying
facilities within the State's access control limits that will be maintained
by the local entity.
- Right of Way Engineering Unit completes relinquishment maps.
Task Duration
References
TASK D436 (500.B)
Send Notification of Contract Approval
Narrative
After the contract is approved, the district is notified.
Initiator
- Office of Office Engineer
Sub-Tasks
- Obtain approval of the contract from Caltrans' Legal Division.
- Send notification of contract approval to the district Construction
Unit.
Task Duration
References