California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 480

Advertise Contract

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D431-D434) 

Milestone
Task Group
 
 Last Update

D431
Complete Resident Engineer File

(480.A)

11/28/94

D432
Prepare Addenda

(480.A)

11/28/94

D433
Conduct Bid Opening

(480.A)

11/28/94

D434
Prepare Contract Award Recommendation

(480.A)

11/28/94


TASK D431 (480.A)

Complete Resident Engineer File

Narrative

The Resident Engineer File is a compilation of pertinent project data developed during the design phase. It includes reports, pertinent letters, quantity calculations, right of way contracts and contractual obligations, materials data and tests, survey notes, environmental document, agreements, permits, etc.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D432 (480.A)

Prepare Addenda

Narrative

Addenda are used to notify prospective bidders of project revisions that may have an impact on the bidding process. Addenda may only be used prior to bid opening, and should only be issued to correct significant errors, omissions, and conflicts. If circumstances indicate the need to issue an addendum, the district should obtain approval to do so.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D433 (480.A)

Conduct Bid Opening

Narrative

Bid openings for projects in Northern California (Districts 1 through 6, 9 and 10) are held in Sacramento on Tuesdays and Wednesdays; those in Southern California (Districts 7, 8, 11, 12) are held in Los Angeles on Thursdays.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D434 (480.A)

Prepare Contract Award Recommendation

Narrative

The districts must submit a recommendation for contract award within five working days following bid opening. Recommendations are required for all projects awarded by the Office of Office Engineer (OOE), regardless of how much the low bid is above or below the Engineer's Estimate.

Initiator

Sub-Tasks

- Low bid exceeds estimate by 10% or more

- An overrun with only one bid

- Low bid is more than 25% below the estimate (20% if the estimate is over $1,000,000)

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 11, 1997.

Go to Top of Document