California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 410

Obtain Right of Way Certification

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D426-D427) 

Milestone
Task Group
 
 Last Update

D426
Determine Method of Right of Way Cleanup

(410.A)

11/28/94

D427
Complete Right of Way Certification

(410.B)

11/28/94


TASK D426 (410.A)

Determine Method of Right of Way Cleanup

Narrative

The right of way process includes more than acquisition of property. The right of way must be cleared of obstructions that were not previously removed. Projects may have workaround clauses, but policy requires the right of way to be cleared and cleaned before the highway contractor is allowed to begin construction on that property.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D427 (410.B)

Complete Right of Way Certification

Narrative

Previous right of way activities performed the calculations, appraisals, negotiations, and acquisitions required for Right of Way Certification. Certification requirements must now be completed so that the project can be advertised.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 11, 1997.

Go to Top of Document