| Complete District PS&E | |||
| Prepare Combined PS&E | |||
| Prepare Draft Contract Documents (Qualified Projects) |
* Milestone 377 is not a PYPSCAN Milestone. It was added to reflect the Office Engineer function in the Districts and Headquarters.
Narrative
The District Office Engineer (DOE) has responsibility for the completeness, quality, and consistency of PS&Es submitted to the Office of Office Engineer (OOE) for processing. The DOE verifies that the design is complete, biddable, and buildable.
Caltrans' goal is to have all projects in "qualified" form when they are submitted to the OOE. A "qualified" project has PS&E that is so complete and accurate that it requires minimal review by OOE for quality, completeness, and consistency. After minor revisions and the addition of "boilerplate" language, the submitted PS&E will be used as the final contract document.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Both the Division of Structures and the district have completed their respective PS&E. The two packages should now be combined.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
For "qualified" projects, the District Office Engineer (DOE) has the authority to prepare the draft contract documents. After preparation and review, the combined PS&E submittal (draft contract documents) should be sent to the Office of Office Engineer (OOE).
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
![]()