California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 275

Send Structures General Plan to District

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D379-D387) 

Milestone
Task Group
 
 Last Update

D379
Request Review of Structure General Plans by District

(275.A)

11/28/94

D380
Conduct Structure Foundation Studies

(275.A)

11/28/94

D381
Prepare Structure Foundation Report

(275.A)

11/28/94

D382
Prepare Structure Plans and Quantities

(275.A)

11/28/94

D383
Review Structure Unchecked Detail Sheets

(275.A)

11/28/94

D384
Obtain Local Entities Concurrence on Falsework Clearances

(275.A)

11/28/94

D385
Obtain Approval of Nonstandard Falsework Clearances

(275.A)

11/28/94

D386
Prepare Structures Specifications and Estimates

(275.A)

11/28/94

D387
Conduct Structures Construction Review

(275.A)

11/28/94

Go to Top of Document


TASK D379 (275.A)

Request Review of Structure General Plans by District

Narrative

The Structure General Plans include bridge type, dimensions, aesthetics treatments, and a cost estimate. District review of the plans is needed before detailed structure design can proceed.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D380 (275.A)

Conduct Structure Foundation Studies

Narrative

The district may have performed limited foundation studies before submitting Bridge Site Plans. These studies should have been provided to the Office of Structure Design for use in the preliminary foundation design. A complete study is required for the final foundation design.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D381 (275.A)

Prepare Structure Foundation Report

Narrative

After the foundation studies are completed, a Foundation Report should be prepared. This is an important element in structure design.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D382 (275.A)

Prepare Structure Plans and Quantities

Narrative

Completion of the District review of the Structure General Plans initiates the development of the Bridge Plans and quantity calculations.

Initiator

Sub-Tasks

- Superstructure

- Substructure

- Type of structure (cast-in-place, prestressed girders, etc.)

- Railings

- End slope treatment, etc.

Task Duration

References

Go to Top of Document


TASK D383 (275.A)

Review Structure Unchecked Detail Sheets

Narrative

During the development of the structure PS&E, appropriate unchecked detail sheets should be sent to the district for review.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D384 (275.A)

Obtain Local Entities Concurrence on Falsework Clearances

Narrative

Bridge construction may involve falsework on local streets and roads. Task D314 identified issues and established initial contact with the local entities. Local entity concurrence on falsework clearances should now be obtained.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D385 (275.A)

Obtain Approval of Nonstandard Falsework Clearances

Narrative

Nonstandard vertical falsework clearances require approval of the OPPD Coordinator. Nonstandard horizontal falsework clearances require approval of the District Director with concurrence from the OPPD Coordinator.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D386 (275.A)

Prepare Structures Specifications and Estimates

Narrative

After the Structure General Plans, checked details, and final quantities have been prepared and reviewed, Structures PS&E is then completed.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D387 (275.A)

Conduct Structures Construction Review

Narrative

This is an Office of Structure Design task that completes structures design. A review meeting should be held to ensure that the Structures PS&E is accurate, practical, and constructable.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 12, 1997.

Go to Top of Document