California State Department of Transportation
|
Task Number |
Task Group |
Last Update | |
| Request Review of Structure General Plans by District | |||
| Conduct Structure Foundation Studies | |||
| Prepare Structure Foundation Report | |||
| Prepare Structure Plans and Quantities | |||
| Review Structure Unchecked Detail Sheets | |||
| Obtain Local Entities Concurrence on Falsework Clearances | |||
| Obtain Approval of Nonstandard Falsework Clearances | |||
| Prepare Structures Specifications and Estimates | |||
| Conduct Structures Construction Review |
| Go to Top of Document |
Narrative
The Structure General Plans include bridge type, dimensions, aesthetics treatments, and a cost estimate. District review of the plans is needed before detailed structure design can proceed.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
The district may have performed limited foundation studies before submitting Bridge Site Plans. These studies should have been provided to the Office of Structure Design for use in the preliminary foundation design. A complete study is required for the final foundation design.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
After the foundation studies are completed, a Foundation Report should be prepared. This is an important element in structure design.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Completion of the District review of the Structure General Plans initiates the development of the Bridge Plans and quantity calculations.
Initiator
Sub-Tasks
- Superstructure
- Substructure
- Type of structure (cast-in-place, prestressed girders, etc.)
- Railings
- End slope treatment, etc.
Task Duration
References
| Go to Top of Document |
Narrative
During the development of the structure PS&E, appropriate unchecked detail sheets should be sent to the district for review.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Bridge construction may involve falsework on local streets and roads. Task D314 identified issues and established initial contact with the local entities. Local entity concurrence on falsework clearances should now be obtained.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Nonstandard vertical falsework clearances require approval of the OPPD Coordinator. Nonstandard horizontal falsework clearances require approval of the District Director with concurrence from the OPPD Coordinator.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
After the Structure General Plans, checked details, and final quantities have been prepared and reviewed, Structures PS&E is then completed.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
This is an Office of Structure Design task that completes structures design. A review meeting should be held to ensure that the Structures PS&E is accurate, practical, and constructable.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
![]()