California State Department of Transportation
|
Task Number |
Task Group |
Last Update | |
| Prepare Right of Way Appraisal Maps | |||
| Prepare List of Fences, Gates, and Potential Excess Land | |||
| Obtain OPPD Approval for Exceptions to Locked Access Gates Policy | |||
| Review Project with U.S. Forest Service | |||
| Determine Final Right of Way and Easement Requirements | |||
| Obtain Approval of Certificate of Sufficiency for Right of Way |
| Go to Top of Document |
Narrative
After receipt of geometric base maps and title reports, Right of Way Engineering prepares right of way appraisal maps for parcels required for the project. The appraisal maps are tied to surveys and Caltrans' construction station lines. The size of the required parcel take, plus the remainder of the parcel are shown, along with all topography, such as: buildings, fences, driveways, water wells, and other existing improvements that affect the appraisal value.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Appraisal maps show existing parcel improvements along with right of way requirements. Engineering details may affect the appraisal value and should be included in the appraisals.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Caltrans policy limits the use of locked access gates on freeways and expressways to Caltrans personnel. Exceptions to this policy must be approved by OPPD.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Many State highway projects require negotiations with the U.S. Forest Service. Right of way for the project is granted by processing a Forest Appropriation Agreement. The right of way is not granted in fee, but easements are documented on the appropriation map.
The U.S. Forest Service was contacted during the early design phase. Now it is necessary to obtain concurrence on easement requirements. The Forest Service will be reimbursed for merchantable timber removed during construction of the project.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
Right of Way appraisal maps are approved by the Deputy District Director for Right of Way. Before approval is obtained, appraisal maps should be reviewed to ensure that the project's right of way requirements are correct.
Initiator
Sub-Tasks
- Drainage
- Earthwork
- Soundwalls
- Maintenance access
- Material sites
- Utilities
- Railroads
- Etc.
Task Duration
References
| Go to Top of Document |
Narrative
At this stage, a Right of Way Certificate of Sufficiency is processed. This indicates that the Project Development Unit has determined which parcels are required.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
![]()