California State Department of Transportation
|
Task Number |
Task Group |
Last Update | |
| Prepare Structure General Plans | |||
| Review Falsework Requirements | |||
| Prepare Railroad Separation Structure Exhibits for the Public Utilities Commission |
Narrative
The Bridge Site Data submittal and the Division of Structures Preliminary Report provide data that is used to prepare the Structure General Plans. Now the Office of Structure Design prepares the Structure General Plans. The plans provide a detailed description of the structure.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
Narrative
After receipt of the Structure General Plans, the district reviews the falsework openings for conformity with standards. The contractor is responsible for structural design of falsework.
Initiator
Sub-Tasks
- Widths and heights of openings
- K-rail
- Need for illumination
- Staging and traffic handling
Task Duration
References
| Go to Top of Document |
Narrative
The Division of Structures (DOS) is responsible for contacts with the Public Utilities Commission (PUC). DOS prepares the necessary exhibits.
Initiator
Sub-Tasks
Task Duration
References
| Go to Top of Document |
![]()