Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 222

Initiate Structures Design

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D313-D315) 

Milestone
Task Group
 
 Last Update

D313
Prepare Structure General Plans

(222.A)

11/28/94

D314
Review Falsework Requirements

(222.A)

11/28/94

D315
Prepare Railroad Separation Structure Exhibits for the Public Utilities Commission

(222.A)

11/28/94


TASK D313 (222.A)

Prepare Structure General Plans

Narrative

The Bridge Site Data submittal and the Division of Structures Preliminary Report provide data that is used to prepare the Structure General Plans. Now the Office of Structure Design prepares the Structure General Plans. The plans provide a detailed description of the structure.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D314 (222.A)

Review Falsework Requirements

Narrative

After receipt of the Structure General Plans, the district reviews the falsework openings for conformity with standards. The contractor is responsible for structural design of falsework.

Initiator

Sub-Tasks

- Widths and heights of openings

- K-rail

- Need for illumination

- Staging and traffic handling

Task Duration

References

Go to Top of Document


TASK D315 (222.A)

Prepare Railroad Separation Structure Exhibits for the Public Utilities Commission

Narrative

The Division of Structures (DOS) is responsible for contacts with the Public Utilities Commission (PUC). DOS prepares the necessary exhibits.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 12, 1997.

Go to Top of Document