California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 010

Approve Project Study Report

(Click on highlighted Task to see detailed information.)

 Planning
Task
Number

Planning Tasks (P045-P075) 

Milestone
Task Group
 
 Last Update

P045
Identify Candidate List

(010.A)

11/28/94

P046
Identify Draft Programming Document

(010.A)

11/28/94

P047
Initiate Tax Measure Project

(010.A)

11/28/94

P048
Obtain Data from Tax Measure Authority

(010.A)

11/28/94

P049
Prepare Supplemental Project Study Report for Tax Measure Projects

(010.A)

11/28/94

P050
Circulate Supplemental Project Study Report

(010.A)

11/28/94

P051
Approve Supplemental Project Study Report

(010.A)

11/28/94

P052
Execute Cooperative Agreement for Preliminary Studies

(010.A)

11/28/94

P053
Approve Programming of Project in Appropriate Document

(010.A)

11/28/94

P054
Obtain "0" (zero) Phase Expenditure Authorization

(010.A)

11/28/94

P055
Request Placement of Project in Federal State Transportation Improvement Program

(010.A)

11/28/94

P056
Review PSR Scope, Cost, and Person-Year Requirements

(010.A)

11/28/94

P057
Obtain Mapping and Surveys

(010.B)

11/28/94

P058
Identify Tentative Project Development Category

(010.B)

11/28/94

P059
Update Materials Information and Traffic Data

(010.B)

11/28/94

P060
Review Preliminary Alternatives, Costs, and Schedules

(010.B)

11/28/94

P061
Prepare Community Involvement Plan

(010.C)

11/28/94

P062
Conduct Value Analysis Study (Project Report)

(010.C)

11/28/94

P063
Review Need for Consultant Services

(010.D)

11/28/94

P064
Initiate Contracting-Out Process

(010.D)

11/28/94

P065
Advertise for Consultant Services

(010.D)

11/28/94

P066
Select Consultant

(010.D)

11/28/94

P067
Negotiate Consultant Contract

(010.D)

11/28/94

P068
Execute Consultant Contract

(010.D)

11/28/94

P069
Conduct Initial Public Information Meeting

(010.E)

11/28/94

P070
Prepare and Distribute Written Notice of Studies

(010.E)

11/28/94

P071
Update Alignments and Geometrics

(010.E)

11/28/94

P072
Obtain Project Development Coordinator's Review of Updated Alignments and Geometrics

(010.E)

11/28/94

P073
Prepare Maps for Environmental Evaluation

(010.E)

11/28/94

P074
Request Environmental Studies

(010.E)

11/28/94

P075
Obtain Access for Environmental and Engineering Studies

(010.E)

11/28/94

Go to Top of Document


TASK P045 (010.A)

Identify Candidate List

Narrative

All projects proposed by Caltrans must compete for limited available funding. Separate priority lists are normally maintained for each highway program (Safety, Rehabilitation, New Facilities, etc.). Each program has an independent priority rating system, usually involving calculation of a Priority Index Number (PIN).

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P046 (010.A)

Identify Draft Programming Document

Narrative

Projects on the State Highway System are proposed for programming in various draft documents. The PSTIP, Proposed Toll Bridge Program, draft SHOPP, and draft TSM Plan are prepared by Caltrans. The RTIP is prepared by the regional agency. Sales tax measure authorities prepare draft Expenditure Plans. Local entities may also have budget plan proposals.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P047 (010.A)

Initiate Tax Measure Project

Narrative

Local transportation authorities are responsible for the development of county sales tax measures to fund transportation projects; however, this is a partnership arrangement with Caltrans. Caltrans' role is to provide support and assistance, especially when concepts, and estimates for scope and cost are developed for specific projects prior to preparation of the sales tax measure ballot.

Initiator

Sub-Tasks

- Prepare estimates.

- List of projects that are candidates for funding by sales tax revenues

- Project Study Reports for candidate projects, if prepared

- Cost estimates for right of way and construction

Task Duration

NOTE: This activity duration will increase if the Project Study Report is not yet prepared.

References

Go to Top of Document


TASK P048 (010.A)

Obtain Data from Tax Measure Authority

Narrative

Specific project information is required for initiating sales tax funded projects following approval by the voters. Most of this information comes from the Project Study Report (PSR) prepared by Caltrans. However, there may be instances where considerable time has elapsed since the PSR was prepared and the tax measure ballot approved. A supplemental PSR may be required and additional data is requested from the local entity.

Initiator

Sub-Tasks

- Expenditure plan

- Strategic plan

- Other information, such as additional maps

Task Duration

References

Go to Top of Document


TASK P049 (010.A)

Prepare Supplemental Project Study Report for Tax Measure Projects

Narrative

If resources are available, Caltrans prepares supplemental Project Study Reports (PSR) at its own expense, for projects on the State Highway System that are financed by county sales taxes. The purpose of the supplemental PSR is to define a programmable project, by combining preliminary project concepts from the PSR together with current engineering and fiscal constraints.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P050 (010.A)

Circulate Supplemental Project Study Report

Narrative

Preparation of a draft supplemental Project Study Report (PSR) and the draft Fact Sheets required input from Caltrans units and affected tax measure authority. Final review should now be obtained.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P051 (010.A)

Approve Supplemental Project Study Report

Narrative

The final step in the supplemental Project Study Report (PSR) process is to obtain approval from the District Director.

Initiator

Sub-Tasks

- District concurrence on the Fact Sheet for exceptions to Mandatory Design Standards; approval of the Fact Sheet for exceptions to Advisory Design Standards

- Project Development Coordinator approval of the Fact Sheet for exceptions to Mandatory Design Standards

- For Interstate System projects, obtain FHWA conceptual approval of the project; as well as approval of the Fact Sheet for exceptions to Mandatory Design Standards, if appropriate

Task Duration

References

Go to Top of Document


TASK P052 (010.A)

Execute Cooperative Agreement for Preliminary Studies

Narrative

Approval of the Project Study Report for a locally funded or a sales tax measure funded project authorized negotiations for a Cooperative Agreement with applicable local entities. This agreement initiates preliminary studies and establishes funding for a cooperative project. After approval of the draft agreement by OPPD (or by use of pre-approved forms), the agreement should be executed by the local entities and the District Director.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P053 (010.A)

Approve Programming of Project in Appropriate Document

Narrative

Projects on the State Highway System, funded in part or in whole with State and federal funds, are programmed in either the STIP, the Toll Bridge Program, the SHOPP, or the TSM Plan.

Tax measure funded projects are programmed in the tax measure authority's expenditure plan.

Locally funded projects are programmed by a local entity funding commitment, which may be supported by an expenditure plan proposed by the entity.

Developer funded projects, if not sponsored by a local entity, are committed to by a letter from the developer.

Initiator

Sub-Tasks

- CTC staff prepares recommendations for STIP proposals.

- CTC adopts STIP, SHOPP, and Toll Bridge Program.

- Caltrans approves the TSM Plan; CTC allocates the funds.

Task Duration

References

Go to Top of Document


TASK P054 (010.A)

Obtain "0" (zero) Phase Expenditure Authorization

Narrative

The "K" phase Expenditure Authorization (EA) is used to record the costs of preparing the Project Study Report (PSR) and the supplemental PSR. The "0" (zero) phase EA is used to develop the project through the project approval phase.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P055 (010.A)

Request Placement of Project in Federal State Transportation Improvement Program

Narrative

Projects using federal funds must be included in the Federal State Transportation Improvement Program (FSTIP) in order to be eligible for funding through the FNM-76 process. Projects located in urbanized areas must also be covered by the Annual Element of the region's RTIP prior to requesting funds for a specific project.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P056 (010.A)

Review PSR Scope, Cost, and Person-Year Requirements

Narrative

During project development, periodic reviews must be made to validate that the project still satisfies project goals and objectives, and to ensure that there are sufficient resources for timely delivery.

Initiator

Sub-Tasks

 

Task Duration

References

Go to Top of Document


TASK P057 (010.B)

Obtain Mapping and Surveys

Narrative

It was important to use accurate mapping for the Project Study Report (PSR), but time requirements may make it difficult to obtain aerial contour mapping. If this was the case, mapping should be ordered when the PSR is approved, in order to provide accurate base maps for environmental studies and the Project Report.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P058 (010.B)

Identify Tentative Project Development Category

Narrative

Project development categories identify projects with similar processing requirements. The PDT determines the project category for a project. On locally initiated projects, the local entity should be involved in the determination.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P059 (010.B)

Update Materials Information and Traffic Data

Narrative

During development of the Project Study Report, available materials information was obtained. Current and forecasted traffic data were also obtained for use in developing alternatives. This information must be updated before starting environmental studies.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P060 (010.B)

Review Preliminary Alternatives, Costs, and Schedules

Narrative

The planning process is dynamic; it requires continuous review. Project alternatives must be reviewed to determine if additional features or alternatives should be studied. The Value Analysis (VA) process is one technique that can be used in evaluating alternatives.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P061 (010.C)

Prepare Community Involvement Plan

Narrative

A Community Involvement Plan is used to facilitate ongoing dialogue with public entities, organizations, private groups, and the public. This plan should cover project features, issues, and impacts.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P062 (010.C)

Conduct Value Analysis Study (Project Report)

Narrative

Most projects should be developed using the Value Analysis (VA) process. For these projects, a VA team will be established. This VA team conducts a VA study of the project.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P063 (010.D)

Review Need for Consultant Services

Narrative

The process of contracting for consultant services requires the participation of involved Caltrans functional units and, when appropriate, the California Department of General Services. After the Project Study Report and project programming have been approved, a prompt decision should be made regarding the need for contracting out engineering or environmental studies, as the contracting process can take considerable time.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P064 (010.D)

Initiate Contracting-Out Process

Narrative

If a decision has been made to contract for engineering or environmental studies, the contract process should be initiated as soon as possible to avoid potential delays.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P065 (010.D)

Advertise for Consultant Services

Narrative

Caltrans has developed standardized procedures for advertising for consultant services to ensure a wide distribution to qualified firms and compliance with applicable laws. Generally, the advertising process is handled by the HQ Consultant Services Branch, in cooperation with the HQ Contracts Service Office.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P066 (010.D)

Select Consultant

Narrative

The Consultant Selection Committee evaluates the consultants' qualifications in order to select the most qualified firm.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P067 (010.D)

Negotiate Consultant Contract

Narrative

Negotiations with the highest-ranked consultant firm begin after the selection process is completed. The objective of negotiations is to obtain consultant services at a cost that is fair and reasonable to both the state and to the consultant. Negotiations are confidential; only those with a need to know should have access to the consultant's cost proposal and Caltrans' estimate.

Initiator

Sub-Tasks

At the same time, the Negotiations Board evaluates the consultant's cost proposal in comparison with the Caltrans estimate.

Task Duration

References

Go to Top of Document


TASK P068 (010.D)

Execute Consultant Contract

Narrative

After negotiations are complete, the consultant contract can be finalized and executed. This requires review and approval by the district, Contracts and Services Office, Legal Division, and if required - the California Department of General Services. The contract is not fully executed until required approvals have been obtained. The consultant may not commence work until the contract has been fully executed and Caltrans authorizes the consultant to proceed.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P069 (010.E)

Conduct Initial Public Information Meeting

Narrative

The initial public information meeting is a key part of the Community Involvement Plan. During preparation of the Project Study Report, contacts were made with the staff of affected local entities. The initial public information meeting initiates involvement of the general public. Affected public and private groups and the media should also be invited.

The meeting is mandatory for Category 1 and Category 2A projects. For Category 2B, Category 3, and Category 4A projects, the meeting should be held if requested or if there appears to be sufficient interest. For Category 4B projects, the meeting should only be held if requested by the local entity. This meeting may also be the scoping meeting for projects involving an EIS.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P070 (010.E)

Prepare and Distribute Written Notice of Studies

Narrative

Written notification of initiation of studies is prepared and sent to interested parties after there is agreement on the study process. This notification is concurrent with the beginning of the environmental process.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P071 (010.E)

Update Alignments and Geometrics

Narrative

Before proceeding with environmental studies, alignments and geometrics should be updated so the impacts may be more accurately determined.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P072 (010.E)

Obtain Project Development Coordinator's Review of Updated Alignments and Geometrics

Narrative

At this stage, concurrence with updated alignments and geometrics should be obtained from the Project Development Coordinator.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P073 (010.E)

Prepare Maps for Environmental Evaluation

Narrative

Environmental effects may be difficult to identify. Many natural resources (trees, parks, etc.) are easily recognized; however, certain plants and animals, as well as wetlands, vernal pools, etc., can only be identified at specific times of the year. To facilitate environmental studies, maps should be prepared that identify areas of potential impacts.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P074 (010.E)

Request Environmental Studies

Narrative

Environmental studies may control the project schedule between Project Study Report and project approval. Studies must be performed on alternatives selected for study. Some studies, such as an archaeological survey or endangered species study, could take two or more years to complete. The date of request for environmental studies is one of five dates that must be reported to the California Legislature.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P075 (010.E)

Obtain Access for Environmental and Engineering Studies

Narrative

The need for rights of entry must be reviewed at this time. Before environmental studies begin, permission must be obtained to enter private properties.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 12, 1997.

Go to Top of Document