California State Department of Transportation

Project Development Procedures Manual (PDPM)

CHAPTER 10 - Formal Project Studies

SECTION 1 - General

This chapter discusses the project development workflow tasks between
Milestones 020 and 140. For details on these tasks, see the
Project Development Workflow Tasks Manual.

Applicability

This chapter covers those projects that had a Project Study Report (PSR) as the project initiation document. It also applies to those projects having a specialized project initiation document that requires further project studies prior to project approval.

For many projects that use a specialized project initiation document (other than the PSR), project studies are complete and project approval is granted when the project initiation document is approved. Chapter 12, Section 4, of this manual identifies those project initiation documents that function as project approval documents and also specifies what conditions need to be met for this to apply. These specialized projects can begin the design process once they are approved and the project has been programmed.

Initiating Formal Studies

The project initiation process produced a PSR or other project initiation document that may include project alternatives. The preliminary scope of each alternative is determined, reliable estimates are prepared, and a feasible schedule is established. When the most likely alternative (or minimum alternative or a stage of the project) is included in an appropriate programming document, formal project studies can begin. Formal project studies should focus on the programmed project unless the programmed project is a stage - in which case the total project would probably be studied.

Project Development Category

The project development process places projects into Project Development Categories, which are defined by various project processing requirements. The Project Development Team (PDT) determines the Project Development Category for a project, as well as the type of required environmental studies. The PDT also addresses other questions: -Is the project Categorically Exempt under CEQA? -Are the project effects environmentally significant? -Is a Negative Declaration or Environmental Impact Report (EIR) required? If an EIR is contemplated, the PDT will undertake formal scoping to determine the extent of required environmental studies.

Engineering Studies

Before environmental studies can begin, preliminary engineering studies are updated and geometric plans are developed for viable project alternatives. These preliminary plans are used as base maps for the required environmental studies.

Environmental Studies

Environmental studies include air, noise, water, wetlands, historical & cultural, parklands, historic & recreation areas, coastal zone, wildlife & plants, and visual aspects. Social, economic, and land-use issues are also addressed, along with specific concerns such as potential hazardous waste sites and right of way impacts.

Community Involvement

A Community Involvement Plan is mandatory and is developed with active participation from local representatives. (See Chapter 22, Article 5.) It is designed to obtain answers to questions such as: -Does the project have community support? -Is the project "right" for the community -How can project impacts be minimized and transportation services be maximized?

Studies Determination

The PDT is responsible for directing and evaluating the studies. An initial public information meeting is held to measure the public support for the project. Additional informational meetings may be required to obtain sufficient support to proceed. Once support is obtained, the PDT proceeds with the studies. Completion of studies leads to preparation of a Draft Project Report and a Draft environmental document or, for a project that is Categorically Exempt/Excluded, directly to the preparation of a Project Report.

SECTION 2 - Engineering Studies

General

Although engineering studies are performed during all phases of project development (including construction), the engineering studies performed following the project initiation phase will support environmental evaluation and project approval. The Project Engineer uses imagination, ingenuity, and technical skill to develop or refine transportation project alternatives to solve a transportation problem.

Effect of Physical Features

Engineering studies begin with the identification of physical features, to establish physical controls and constraints. Physical features include terrain (flat, hilly, mountainous), material (dirt, sand, rock), improvements (buildings, drainage structures, utilities), environmental concerns (flora, fauna, wetlands), etc.

Scoping Project Features

Once physical controls are defined, project features are scoped. The following questions are posed: -What Level of Service (LOS) is obtainable? -What design speed is most suitable for the LOS and physical features? -What typical section is needed to accommodate traffic? -Is the proposed project cost effective?

Importance of Accurate Mapping

Adequate mapping is necessary as a basis for accurate engineering studies. The Right of Way Branch needs accurate maps to make estimates. Environmental studies require good mapping, particularly for cultural and biological studies. Windshield surveys may help produce estimates, but good project scope and good estimates need good maps.

Accurate maps are not always available early, so available mosaics or strip maps should be systematically checked in the field to ensure reasonableness. The mapping prepared in the project initiation phase should be checked, updated and expanded as required (as-builts, mosaics, strip maps, aerial contour maps).

It is essential that appropriately accurate mapping and photography be obtained on each route study or major improvement project. In rural areas, foothills, or mountainous terrain, mapping on a scale of 1:2000 with two meter contours is considered appropriate; in some cases, mapping at a smaller scale may be appropriate in particularly rugged terrain. In urban areas, larger scale maps with closer contour intervals usually will be desirable; a scale of 1:500 or 1:1000 is preferable.

Under special circumstances where the combination of terrain and development is especially critical, the use of photo-contour maps should be considered. In relatively flat areas, mosaics supplemented by elevation data or correlation with USGS maps may be satisfactory.

For further information on mapping, see the Guidelines for Preparation of Project Study Reports in Appendix L or Chapter 9, Article 3, of this manual, as well as Chapters 3 and 5 of the Drafting and Plans Manual.

Phases of Engineering Studies

Early engineering studies began with the identification of the transportation problems and the identification of reasonable alternative solutions. The early feasibility studies used sources such as the Transportation Concept Report, District System Management Plan, Regional Transportation Plan, Congestion Management Program, and initial engineering studies, which served as the basis for the project initiation document. They addressed such questions as: -What is the problem? -What are the possible solutions? -Can significant environmental impacts be avoided? -What is the cost?

Note: Since formal environmental studies are not undertaken during the project initiation phase, there was no public input beyond that provided by local agencies, regional agencies, or resource and regulatory agencies.

At the "formal project studies" stage, formal engineering studies expand the project initiation studies, as necessary. These and subsequent engineering studies reflect public input and the need for environmental evaluation and project approval.

Engineering Standards

By adherence to the engineering standards in the Highway Design Manual, engineering studies should lead to a serviceable, high quality product. These standards must be met unless an exception to Mandatory Design Standards is processed and approved.

Geometric Drawings

On location studies, separations and interchanges for each alternative studied are shown on Draft Project Report (DPR) and environmental exhibit maps, either by schematics or by delineating the geometric pattern of these facilities. Because interchange arrangements could have a deciding effect upon the relative traffic service provided by the different studied locations, consideration must be given to the type and location of interchanges.

Where special problems are involved, such as provision for local service ramps in the proximity of freeway-to-freeway interchanges, the working drawing delineating the geometric pattern of these facilities that are used as the basis of estimates must be cleared with the PD Coordinator or Geometric Reviewer for feasibility prior to submittal of a DPR for approval.

Scope of Engineering Studies

Engineering studies go hand-in-hand with environmental studies. The scope of the studies should be sufficient to complete the environmental evaluation of the project and to reach a decision on project approval.

Engineering studies produce a line (location), grade (elevation), typical section (width), and cost for each alternative under consideration. Engineering studies include: geological, advance structures, drainage, capacity, and traffic management. Value Analysis studies are also conducted to ensure that concepts are economically feasible. The information discussed in the PSR should be reviewed and the data expanded and updated as necessary.

PD Coordinator Review

In all cases, geometric and grade line alternatives should be reviewed by the PD Coordinator or Geometric Reviewer prior to preparation of the DPR.

SECTION 3 - Environmental Studies

Engineering/ Environmental Comparison

While the engineering studies described in Chapter 10, Section 2, do consider environmental impacts, they concentrate primarily on design standards, operating characteristics, and cost. Environmental studies focus on the environmental impacts of the project alternatives, giving further consideration to how environmental, social, and economic impacts can be avoided or significantly reduced.

Environmental Effects Need Specific Studies

A project's direct effect on environmental resources (wetlands, historic buildings, etc.) and its potential effects on less obvious resources (air quality, noise, water, etc.) require study before project decisions can be made.

Preliminary environmental evaluations were performed in both the system planning and the project initiation stages. These basic studies identified environmental issues and anticipated adverse effects. Avoidance alternatives, if required, should also have been considered at that time. If an avoidance alternative was required, and a reasonable avoidance alternative existed, further consideration of non-avoidance alternatives should have ceased.

Lead Agency

For projects that are not entirely Caltrans projects, the assignment of the Lead Agency is specified in the Scope of Work attached to a Cooperative Agreement, or in a Memorandum of Understanding. Chapter 2, Section 7, of this manual discusses the determination of Lead Agency. The Cooperative Agreement Manual contains instructions on Agreements.

Begin Environmental Studies

Formal environmental studies for project development begin after programming, after updating the studies used to develop the PSR (traffic forecasts, etc.), and after adequate mapping has been prepared showing the area of potential impact. For certain Project Development Categories (see Chapter 8, Section 5, Figure 1, and Chapter 22, Article 5), initial public meetings are held to assist the PDT in reaching agreement on the project study process. Then, for various Project Development Categories (see Chapter 8, Section 5, and Chapter 22, Article 10), a written notice of studies is issued to provide public notification of the process that will be followed.

At the same time, the Project Manager sends a memo requesting the Environmental Unit to begin environmental studies. The memo must provide specific project information and must specifically request a response from the Environmental Unit, since it establishes an important milestone date (Milestone 020: Begin Environmental Studies).

Types of Studies

The type and extent of environmental studies vary with the location and complexity of the project. Typically, the studies need to address air quality, noise impacts, water quality, wetlands, coastal zone infringement, floodplains, wildlife and plants, historic and cultural resources, social and economic changes, park lands and recreational areas, hazardous waste, energy, and visual effects.

Federal Concerns

The federal government's involvement in the project development process is described in Chapter 2, Section 8. Particular attention, however, must be given to FHWA's involvement with the following federal executive orders, environmental laws and their implementing regulations, and agreements:

Alternative Studies

Environmental studies are performed for all viable alternatives (see Chapter 8, Section 6). The environmental effects and possible required mitigation are quantified to assess the feasibility of each alternative.

Responsibility of PDT

The Project Development Team (PDT) has the responsibility to direct and evaluate the project studies, to determine if any project rescoping is needed, and to develop new alternatives, if required. When consensus is reached, the PDT determines the appropriate level of environmental evaluation. If an environmental document is required, the PDT directs its preparation.

Notice of Preparation / Intent

If the PDT determines there is the potential for significant environmental effects and that preparation of an EIR/EIS is required, the District Environmental Unit prepares and distributes a Notice of Preparation (CEQA) and requests FHWA to issue a Notice of Intent (NEPA). Refer to the Environmental Handbook for current instructions.

Continuous Environmental Involvement

Environmental involvement should continue throughout the entire project development process. During the design phase, in construction, and during maintenance activities, decisions must consider environmental concerns.

The above discussion highlights important environmental requirements. For additional information, please refer to the Environmental Handbook.

SECTION 4 - Identifying Project Alternatives and Mitigations for Impacts

General

Caltrans subscribes to what can be called a "plan-to-ground" philosophy in its approach to environmental analysis and project development. This plan-to-ground philosophy calls for the separate and independent evaluation and discussion of each viable project alternative, covering only its own specific impacts upon its surrounding environment. This philosophy is intended to develop a Draft environmental document that avoids comparisons "between" alternatives.

The comparison between alternatives ("plan-to-plan" philosophy) is reserved for the later evaluation process where a Preferred Alternative may be offered, and where the comparisons may be used as an evaluation tool by the ultimate decision maker.

The objective at this stage of alternatives analysis, is to enter the public review process with a bias-free presentation, such that the results of the public review process, after evaluation, will dictate the selection of the Preferred Alternative.

The following six headings chart the formal project studies process to develop viable alternatives for the public hearing stage.

Stating the Purpose and Need

The "Purpose and Need" section of an environmental document is the key to developing a document that is defensible in court. This section provides the foundation for identifying the full range of possible alternatives, and determining which of these alternatives are reasonable.

When preparing this section, it's important to have early identification of the potential environmental issues and a general knowledge of the associated regulatory requirements. This is beneficial because the "Purpose and Need" section must not only substantiate the project as a whole; it must also justify each of the resulting significant environmental impacts, uses of protected resources, and impacts on hazardous wastes.

It is important to present this section in terms readily understood by the public. Written text can be enhanced by high-quality graphics and non-technical explanations.

It is prudent to often re-examine the project's "Purpose and Need" statement to reflect community input, funding constraints, and the discovery of additional impacts.

The following paragraphs discuss items to be considered when developing the "Purpose and Need" section. The items discussed are not all inclusive. It is important that the specific objectives provide a comprehensive point of reference with which to compare possible alternatives.

Clear Project / Neutral Statement

A clear and defensible "purpose and need" is a requisite of quality project planning and development. It is the basis for making decisions. The "Purpose and Need" section of the environmental document must clearly demonstrate the purpose and need for the transportation improvement. The discussion should be presented in a project-neutral fashion against which the various alternatives can be compared. This definition of purpose and need will be weighed by the public and the decision makers against the documented impacts of the project; as such, it deserves thorough analysis and discussion. The following paragraphs provide discussion on a variety of "Purpose & Need" approaches.

Is there a federal, State, or local government mandate for the project? -Are the local, regional, and State land-use and transportation plans based on the assumption that the project will be implemented? -Is there a history of commitment toward ultimate implementation? -Have there been elections, special legislation, or other decisions or commitments mandating consideration of the project?

Is the project necessary to correct an existing or potential safety hazard? -Is the existing accident rate high? -Why? -How will the project improve it? For ease of public understanding, the objective should relate to how many fewer accidents, injuries, and fatalities could be expected to occur within the project area through the design year.

Will the project provide a connecting link in the regional or area-wide system of transportation modes that would enhance utility and/or efficiency? As an example, will the project eliminate a gap between two improved portions of the system and thereby contribute to more consistent user expectations? If so, what will be the benefits to the user?

Are there inappropriately high maintenance costs that can be substantially lowered by the project? If so, outline the data. -Are there inappropriate user weight or size restrictions that would be eliminated? If so, what will be the benefit of removing these restrictions? -Is the existing facility in danger of partial or complete loss of service unless the project is completed? If so, what is the anticipated time frame for such loss of service?

Is the capacity of the present facility adequate for the present and projected demand? For the ease of public understanding, it is necessary to explain the terms "capacity" and "levels of service". The existing and expected levels of service are to be outlined, and then compared to the minimum standards. A concept more easily understood, is "total or cumulative time delays". Accordingly, it is also appropriate to document the existing delays, how they compare to unconstrained flows, and what they are expected to be with and without the project.

With flexible funding, demand needs to be evaluated comprehensively. For example, even if there is congestion on the State highway, it may not necessarily be State highway traffic; it could be local traffic that could be encouraged to remain on local facilities. Under these conditions, problems and solutions need to be looked at more creatively.

When discussing future demands, it is very important to be consistent with the environmental document's strategy for addressing growth and cumulative impacts. The traditional approach is to use transportation projections from, or consistent with, those of the local or regional transportation planning agency. These projections are based on the best available local and regional land-use plans. This facilitates the position that land-use development and transportation facilities are planned together. With this, the question of growth and cumulative impacts can most often be addressed in a relatively conclusive manner.

An exception to this traditional approach is where there are specific economic developments (e.g. convention centers, sports complexes, etc.) or other land use changes that are directly tied to the implementation of the proposed project. In such cases, the transportation projections and cumulative impacts should address these secondary changes.

Is the existing facility resulting in unacceptable social, economic, or environmental impacts that are able to be eliminated with the project?

Are there limits to the amount of financial resources available to address the identified problems? If so, what are these limits? -Is it possible to increase these resources? If not, why not? -Can part of the "Purpose and Need" be addressed in a cost-effective manner within these limits?

Identifying Possible Alternatives

The following range of options are required to be addressed when project alternatives must be formally considered. See Chapter 8, Section 6, of this manual for more details.

Formal Alternatives

Limit Number of Reasonable Alternatives

When there is a large number of potentially reasonable "build" alternatives, it is only necessary to present a representative number of the most reasonable examples, covering the full range of options. Often, several alternatives are actually variations of a single alternative and would be more appropriately treated as design variations.

Impacts of Alternatives

Again, as with the development of the "Purpose and Need" statement, it is important to keep in mind the significant environmental impacts, uses of protected resources, and impacts on hazardous wastes that are likely as a result of the proposed alternative. This basic information will assist in identifying quality alternatives, and will improve the ability to defend the final selection process.

Eliminating Unreasonable Alternatives

Consider Only Reasonable Alternatives

When the formal consideration of alternatives is required, all reasonable alternatives should be evaluated in a comparable level of detail. The Council of Environmental Quality's "Questions and Answers about NEPA" states that:

Reasonable alternatives include those that are practical or feasible from the technical and economic standpoint and using common sense, rather than simply desirable from the standpoint of [FHWA/Caltrans].

Criteria for Rejecting Alternatives

A project alternative may be rejected as unreasonable for any of the following reasons:

Test for Reasonableness

The most direct test of reasonableness is: "Does the alternative meet the project's purpose and need?" This is one of the key reasons why the project's "Purpose and Need" statement is so important. Each alternative is compared to each specific objective in the "Purpose and Need" statement. Only those alternatives that fulfill the major objectives will be determined to have passed this test of reasonableness. However - required avoidance alternatives may still need to be carried forward if they were not eliminated in an acceptable manner in a previous environmental process.

It is important to review the reasonable "build" alternatives to insure that they are consistent with the planning or design concept and scope, or if not, to consider revising the planning or programming documents. (Refer to Chapter 8, Section 1.)

"First Cut" of Alternatives

It is important to recognize that this is only the "first cut" of the alternatives. At this point, adverse impacts are to be evaluated only in general terms; harm to specific protected resources should not be considered. The difficult task of weighing the relative value of, and assessing the relative harm to, the affected protected resources is simplified by delaying the process until the nonviable alternatives have been rejected: the appropriate time for such a task is during the selection process for determining the Preferred Alternative (see Chapter 12, Section 2). For certain protected resources, if "avoidance" alternatives are available, no impacting alternatives may be allowed for consideration.

Document the Elimination of Specific Alternatives

The environmental document must briefly explain why eliminated alternatives were found to be unreasonable. Once documented, no additional consideration of such alternatives is required.

Identifying Specific Effects of Each Alternative

Each alternative under consideration is examined for its full range of environmental impacts. Special studies are undertaken that focus on the potentially significant effects. Each alternative's significant adverse effects on the environment are clearly identified and described in the environmental document.

Determine if Additional Alternatives Need to be Developed

Following completion of detailed environmental studies, a review is conducted of the project alternatives under consideration. This review is performed to re-evaluate the "Purpose and Need" statement, and the range and reasonableness of the alternatives.

Identifying Reasonable Mitigation Measures

All reasonable mitigation measures are identified for each adverse environmental effect expected as a result of each alternative considered. Unavoidable significant effects, if any, are documented for each alternative. Using this information, a final review is conducted to determine the type of environmental document needed. Normally this determination would be to proceed with the Draft EIR/EIS. However, it could be to complete the Initial Studies/Environmental Assessment and prepare a Negative Declaration.

SECTION 5 - Draft Project Report

ARTICLE 1 - General

Purpose of Draft Project Report

The Draft Project Report (DPR) is a decision document. It is only used when there is a Draft environmental document (DED). The purpose of the DPR is to document the need for a transportation project, to summarize key points from the Draft environmental document, and to summarize the studies of the scope, cost, and overall impact of alternatives so that the decision maker can make an informed decision on whether or not to proceed to the public hearing phase of project development.

DPRs are used for Project Development Categories 1, 2, 3, and 4; they must include a DED prepared in accordance with the Environmental Handbook. DPRs are not applicable to Category 2B or 3 projects that are determined to be Categorically Exempt.

Authorization for Public Hearing

When a Draft environmental document (DED) is required, approval of the DPR grants approval to release the DED to the public. In accordance with the PDT's recommendation in the DPR, the public may be (1) invited to a public hearing, (2) given an opportunity for a public hearing, or rarely, (3) the public hearing process may be waived altogether (but only if determined unnecessary on a Category 3 or 4 project that has no federal involvement or it is a Federal Categorical Exclusion under NEPA).

Authorization to Circulate DED

If there is any federal involvement in a transportation project, a separate approval must be obtained to circulate the DED (see Environmental Handbook) for projects without federal involvement, approval of the DPR grants authorization to circulate the DED.

Project Approval

Project approval for Category 1 through Category 4 projects is made after: (1) evaluation of the responses to the DED, (2) completion of the public hearing process, (3) selection of a Preferred Alternative, and (4) completion of the FED.

Caltrans' project approval action is recommended in the final version of the Project Report and is authorized by approval of the Project Report. See Chapter 12, "Project Approvals and Changes to Approved Projects", for details.

Coordination with PSR

Draft Project Reports and Project Study Reports (PSRs) require similar information, acquired at different points in time. The PSR is preliminary in nature and does not benefit from knowledge acquired from detailed environmental studies. When preparing the DPR, appropriate PSR data should be updated prior to its insertion into the DPR; appropriate summary data from the environmental studies should also be included.

Mapping & Costs

Since the DPR is used to document engineering decisions and to determine the proposals and alternatives presented to the public, it is essential that accurate mapping be used. Project costs (roadwork, structures and right of way) for all project alternatives are calculated to enable a realistic comparison of alternatives.

Notify Local Agencies of Right of Way Needs

If the DPR is a first determination that specific right of way parcels may be required, the appropriate city or county planning department should be notified, in compliance with Streets and Highways Code, Section 103.65.

Approval by District Director

DPRs are approved by the District Director or a deputy who has been delegated that authority.

Submittal to Design and Local Program

After approval, two copies of the final document should be forwarded to DLP, Attention: Draft Project Report.

Approval of Changes

Once a project is programmed in a programming document, the project description (type of work, limits, and cost) defines the overall project scope. District Directors are responsible for project delivery (including approval of changes up to certain thresholds). When any threshold is exceeded, Headquarters' approval of the change is required before a new cost, scope, or schedule will be proposed to be included in the programming document (See Chapter 6, "Project Cost, Scope, and Schedule Changes"). Traffic Systems Management (TSM) changes will be accomplished in accordance with the TSM Program Guidelines adopted by the CTC.

See Chapter 12, Section 6, of this manual for a discussion on revisions to approved Project Reports.

ARTICLE 2 - Format and Content

General

A DPR contains the documentation and data necessary to support a public hearing discussion of the proposed alternatives. Most of the people who read the DPR will not be familiar with the proposal; therefore, the information in the DPR should be of sufficient depth and scope to provide evidence to the reader that there is a need for a project.

All DPRs should answer these three basic questions:

Engineering and Environmental Data

The DPR is an engineering report. The DED, on the other hand, is not an engineering document. It is a full disclosure document, and must be attached to the DPR to provide details of the environmental studies. The DPR contains introductory and engineering material and other information that would not be appropriate in the DED, and briefly summarizes pertinent data from the attached DED. Do not unnecessarily repeat what already exists in the DED. The ultimate objective is to produce a document that secures necessary project approvals.

Project Report Outline

The PR preparation guidelines and outline are located in Appendix K. They cover both the Draft Project Report and the Project Report, which is discussed in Chapter 12, Section 3, of this manual.


 Table of Contents

 Expanded Table of Contents

  Index

 PDPM Home Page 

 Design Home Page


For questions or feedback concerning this web site email: ranjeet.bagha@dot.ca.gov

This web site last modified July 1, 1999.

Go to Top of Document