CHAPTER 7 - Uniform File System

SECTION 1 - General Guidelines

Overview

This section provides an overview and rationale for the Project Development Uniform File System. Chapter 7, Section 2, provides a directory and instructions for the project development records that are filed in the Uniform File System.

Responsibility for Managing the File System

The Uniform File System is to be used for all Caltrans projects - regardless of the size or type of project. The originating unit should start the file system as soon as preliminary studies can identify the project. The originating unit may retain copies of material needed for backup on their own studies, but the basic categorized file should be transferred to the Project Engineer (PE) at the appropriate time.

For projects that are transferred between districts or the Office of Central Design, the source district and the consulting unit should determine, at the time of transfer, how their respective units will maintain the project's file system. Local agencies and private consultants shall use the Uniform File System classification scheme for any records exchanged with Caltrans.

Filing Strategies

Many letters and reports cover more than one project issue. Consequently, items will be classified and filed according to the source that generated them, rather than by subject. (Filing by subject area would result in extensive duplication of materials because correspondence and reports would have to be updated for all relevant subject areas.)

The PE should use personal discretion when creating sub-categories for filing purposes. Large projects generate enough correspondence in some categories to require creation of subcategories. No master index will be required, as the categories in the Uniform File System provide adequate identification for timely retrieval.

Projects that are staged into separate contracts for construction (e.g., for grading, paving, or structures) should share the same project file. Material should be duplicated for the respective Resident Engineer's file, but the Project History File (permanent project file) should not be assembled until after completion of all stages.

Projects considered to be initial development for an ultimate future project (e.g., initial two-lane expressway to be expanded to full freeway) should have their own, completed Project History Files. The files should include sufficient data to allow for the future project development - even if the work is not yet programmed.

Projects that are split from larger projects into more manageable segments, should stand on their own: a Resident Engineer's file and a permanent Project History File should be assembled for each segment. It is prudent to break out or duplicate material at an early date, for use as a working file for the PE, and as a source for subsequent files.

Project History File

A Project History File (the permanent project file) should be compiled for all completed projects. The file consists of selected project development records and final project construction records. These are to include all letters, memos, reports, etc. that document project decisions, or that would be useful (or required) to develop a subsequent project.

The Uniform File System Directory (Chapter 7, Section 2) indicates which project development records should be included in the Project History File. The Legal Division has approved these designated items, and the file should not be cluttered with routine records not officially designated for inclusion.

When the construction project is completed, the PE should initiate assembly of the Project History File by transmitting designated records to the Construction Unit. The Construction Unit should either compile the Project History File or transmit the data to the assigned district unit for compilation. The completed Project History File should be permanently filed in a convenient, central file location within the district.

As-Built Plans

As-built plans will continue to be stored on microfilm for permanent records. The automated records management system now under study is anticipated to be able to digitize "as-builts" with equipment such as optical scanners. This system will produce first-quality reproductions and will alleviate present storage problems.

SECTION 2 - Directory and Instructions

Overview

These instructions pertain to the directory for the project development records that should be filed in the Uniform File System. The directory follows these instructions.

"Category" Heading

The first heading in the directory is "CATEGORY." The Project Development Uniform File System has six major categories, as follows:

100 Project Control

200 Project Approval Process

300 External Project Design Correspondence

400 Intra-District Project Design Correspondence

500 Contract Preparation

600 Project Miscellaneous

These categories shall be used for all projects, regardless of size. Major projects shall use the complete system as shown. Smaller projects, with limited amounts of correspondence, may not require the total breakdown.

"Record Type" Heading

The second heading in the directory is "RECORD TYPE." This column describes the material to be included in each category.

"PHF" Heading

The third heading (PHF) stands for "PROJECT HISTORY FILE." This column indicates if the record should be filed in the Project History File.

Explanation of Categories

Category 100 covers project control.

Category 200 is a resource file covering the Project Approval Process. The file should contain only the specified documents and should not be cluttered with routine correspondence. All routine correspondence leading to the various project approval documents should be filed in Categories 300 and 400, as applicable.

Category 300 should contain correspondence between all district sources and external sources, except as noted above. Copies of project correspondence between HQ units should be filed under Category 310.

Category 400 is a source file to contain correspondence between district units.

Category 500 should contain all plans and calculations for design. Preliminary studies and plans should be filed in Category 200. All other plans, whether flat filed in drawers or rolled and placed in bins, are labeled with the appropriate Category 500 breakdown. Likewise, calculation sheets, whether in binders or file cabinet folders, should be labeled accordingly.

Category 600 covers miscellaneous items and is self-explanatory.

Oversized Materials

Attachments to letters that are too bulky for filing in regular files are referenced to the letter by date and category breakdown and then filed in separate envelopes or bins with the appropriate index label.

File Folders, Index Tabs, Filing Strategy

Index folders or index tabs are not furnished by Headquarters. The following file system directory pages may be reproduced and filed with the project file. Index tabs can be used to identify the six major Uniform File System categories. Copies of the file system directory can be used as dividers, providing a handy reference for correct filing and compilation of the Project History File.


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(100 - 143)

CATEGORY

RECORD TYPE

PHF
100 PROJECT CONTROL

110 EXPENDITURES

111 Expenditure Authorizations 111.01 Planning phase (0)

X
111.02 Design phase (1)

X
111.03 Construction phase (3)

X
111.04 Other phases as needed

X
111.08 FNM-76 Requests

X
112 Personnel Costs 112.01 Project Design Costs

X
112.02 Final Project Design Costs

X
112.02 Other department costs, Final Project Costs

X
120 DESCRIPTION

121 Project Description 121.01 Project Description and how determined
122 Post Mile Determination 122.01 Calculations & backup data
130 PROGRAMMING AND PROGRESS

131 Programming Data 131.01 RTIP, PSTIP, STIP, SHOPP, TSM, etc.
for project

132 PYPSCAN 132.01 PYPSCAN milestone dates
132.02 Schedule Calculations
132.03 Schedule Change Approvals

X
133 Progress Reports 133.01 Monthly Project Progress Charts
140 PROJECT COST ESTIMATES

141 Project Cost Estimates 141.01 Log of Project Cost Estimates
141.02 Cost Estimate Backup Data
142 Project Cost Increase 142.01 Cost Change Approvals

X
143 Miscellaneous Project Estimates 143.01 Study Estimates for Project Alternatives, etc.

PHF = Project History File

PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(200 - 223)

CATEGORY

RECORD TYPE

PHF
200 PROJECT APPROVAL PROCESS

210 PRELIMINARY STUDIES

211 Project Initiation 211.01 Documents that identify the problem

X
211.02 Feasibility, Justification or Concept Report

X
211.09 Approvals to proceed

X
212 Project Authorization 212.01 PSR, PSSR, NBSSR, PSR/PR, etc.

X
212.09 Concept Approval

X
212.10 Scope Change Approval

X
212.19 CTC Long Lead Time Concurrence

X
212.29 Approval to Cease Work

X
213 Planning Studies 213.01 Written notice of Initiation of Studies

X
213.02 Corridor or Route Location Studies

X
214 Alternatives 214.01 Preliminary Plan and Profile Studies of Alternatives
214.02 Impacts of Alternatives
214.09 Approval of Alternatives
220 PROJECT DEVELOPMENT TEAM

221 PDT Assignments 221.01 Authorizing Assignment Letter
222 Project Category Assignment 222.01 Determination of Project Category, Major/Categorical Exclusion, Significant/Non-Significant

X
223 PDT Meeting Memos 223.01 Minutes or memos
223.09 Project Approval memos by PDT

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(230 - 244)

CATEGORY

RECORD TYPE

PHF
230 ENVIRONMENTAL

231 Draft Environmental Document


231.01 Environmental Assessment

X
231.02 Circulated Draft & cover letter

X
231.03 Written notice of EIS preparation

X
231.04 Published technical reports

X
231.05 Floodplain Evaluations

X
231.06 Draft 4(f) Document

X
231.09 Approval to Circulate

X
231.10 Mailing list

X
232 Final Environmental Document 232.01 Distributed Final and Cover Letter

X
232.09 Approval to distribute

X
232.19 Findings and Notice of Determination

X
232.29 Record of Decision or FONSI

X
232.30 Mailing list

X
233 Public Notices of Availability 233.01 Public notices from newspapers

X
233.02 Copy of Federal Register entry

X
234 Scenic Highway 234.01 Scenic Highway Study

X
234.09 Approvals

X
240 PROJECT APPROVAL

241 Project Work Plans 241.01 Copies of Project Work Plans
242 Draft Project Report 242.01 Drafts with intradistrict comments
242.02 Draft Project Report

X
243 Preferred Alternative 243.01 Preferred Alternative Selection

X
244 Project Report 244.01 Project Report

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(245 - 262)

CATEGORY

RECORD TYPE

PHF
245 Design Standard Exceptions 245.09 Documentation of Exceptions from Mandatory Design Standards

X
245.10 Documentation of Exceptions from Advisory Design Standards

X
246 Route Adoption 246.09 CTC Report, Resolution, Map

X
247 New Connections 247.09 CTC Report and Resolution

X
247.10 FHWA Approval

X
250 PUBLIC HEARING PROCESS

251 Pre-Hearing Meetings 251.01 Initial Meeting documentation

X
251.02 Scoping Meeting documentation

X
251.03 Map Showings, Informational Meetings, other Pre-Hearing documentation

X
252 Hearing Arrangements 252.01 Notices of Hearing to HQ
252.02 Arrangements for Hearing Officer
253 Public Hearing Notices 253.01 Public notices from newspapers

X
254 Record of Hearing 254.01 Transcript, comments, etc.

X
254.02 Record of Hearing

X
260 PROJECT AGREEMENTS

261 Cooperative Agreements and Reports 261.01 Cooperative Agreement Report

X
261.09 Draft Agreements(s) and submittals to HQ
261.10 Approvals from HQ

X
261.11 Executed Agreements

X
262 Freeway Agreements 262.01 Draft and submittals to HQ
262.09 Approvals from HQ

X
262.10 Executed Agreements with map

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(263 - 274)

CATEGORY

RECORD TYPE

PHF
263 Interagency Agreements 263.01 Drafts and submittals to HQ
263.09 Approvals from HQ

X
263.10 Executed Agreements

X
264 Highway Improvement Agreements 264.01 Drafts and submittals to HQ
264.09 Approvals from HQ

X
264.10 Executed Agreements

X
265 Maintenance Agreements 265.01 Drafts and submittals to HQ
265.09 Approvals from HQ

X
265.10 Executed Agreements

X
270 PERMITS

271 State Agency Permits 271.01 Drafts
271.09 Approvals

X
271.10 Executed permits

X
272 Federal Permits 272.01 Drafts
272.09 Approvals

X
272.10 Executed permits

X
273 Local Agency Permits 273.01 Drafts
273.09 Approvals

X
273.10 Executed permits

X
274 Encroachment Permits 274.01 Drafts and submittals to HQ
274.09 Approvals by HQ and FHWA

X
274.10 Executed permits

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(300 - 341)

CATEGORY

RECORD TYPE

PHF
300 EXTERNAL PROJECT DESIGN CORRESPONDENCE

310 HEADQUARTERS & DISTRICT CORRESPONDENCE

311 Headquarters (except Division of Structures) 311.01 Memos between the district and various HQ units
312 Districts 312.01 Memos between districts
320 DIVISION OF STRUCTURES CORRESPONDENCE

321 Structures 321.01 Memos to and from Structures Design
321.09 Approval memos from HQ

X
322 Structure Studies and Reports




322.01 Advanced Planning Studies
322.02 Bridge Site Submittal
322.03 Preliminary & Foundation Reports

X
322.04 General Plans
322.05 General Details
322.06 Retaining Wall Site Submittal & Plans
322.07 Noise Barrier Site Submittal and Plans
322.08 Structural Adequacy Studies

X
322.09 Special Studies
330 FEDERAL AGENCY CORRESPONDENCE

331 Federal Agencies 331.01 Letters to and from various federal agencies
331.09 Letters affecting project decisions

X
340 STATE AGENCY CORRESPONDENCE

341 State Agencies 341.01 Letters to and from various State agencies
341.09 Letters affecting project decisions

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(350 - 382)

CATEGORY

RECORD TYPE

PHF
350 LOCAL AGENCY CORRESPONDENCE

351 Cities 351.01 Letters to and from various cities
351.09 Letters affecting project decisions

X
352 Counties 352.01 Letters to and from various counties
352.09 Letters affecting project decisions

X
353 Area-Wide Agencies 353.01 Letters to and from various area-wide agencies (COG, etc.)
353.09 Letters affecting project decisions

X
354 Other Agencies or Special Districts 354.01 Letters to and from various agencies or districts (school districts, assessment districts, etc.)
354.09 Letters affecting project decisions

X
360 ELECTED-OFFICIAL CORRESPONDENCE

361 Elected Officials 361.01 Letters to and from elected officials
361.09 Letters affecting project decisions

X
370 PUBLIC CORRESPONDENCE

371 Individuals 371.01 Letters to and from individuals
371.09 Letters affecting project decisions

X
372 Private Groups 372.01 Letters to and from Private Groups
372.09 Letters affecting project decisions

X
380 MEMOS TO FILE (EXTERNAL)

381 Phone Call Documentation 381.01 Phone call documentation
381.09 Phone call documentation affecting project decisions

X
382 Informal Meetings/Discussions 382.01 Notes of informal meetings
382.09 Notes affecting project decisions

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(383 - 386)

CATEGORY

RECORD TYPE

PHF
383 Headquarters Reviews 383.01 Notes of reviews
383.09 Notes affecting project decisions

X
384 FHWA Reviews 384.01 Notes of reviews
384.09 Notes affecting project decisions

X
385 CHP Reviews 385.01 Notes of reviews
385.09 Notes affecting project decisions

X
386 Other Agency Reviews 386.01 Notes of reviews
386.09 Notes affecting project decisions

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(400 - 453)

CATEGORY

RECORD TYPE

PHF
400 INTRADISTRICT PROJECT DESIGN CORRESPONDENCE

410 DRAINAGE

411 Drainage Correspondence 411.01 Memos to and from Hydraulics Unit
411.02 Preliminary Drainage Report

X
411.03 Justification of Alternatives
411.04 Final Drainage Review
412 Drainage Studies 412.01 Design Discharge Calculations

X
412.02 Floodplain encroachment

X
412.03 Rock slope protection sizing

X
412.04 Special Studies

X
420 ENVIRONMENTAL

421 Environmental Correspondence 421.01 Memos to and from Environmental Unit
430 LANDSCAPING

431 Landscaping Correspondence 431.01 Memos to and from Landscaping Unit
440 MATERIALS

441 Materials Correspondence 441.01 Memos to and from Materials Unit
441.02 Materials Reports

X
441.03 Pavement Deflection Studies

X
441.04 Special Materials Studies

X
450 OPERATIONAL

451 Maintenance Correspondence 451.01 Memos to and from the Maintenance Unit
452 Construction Correspondence 452.01 Memos to and from the Construction Unit
453 Traffic Operations Correspondence 453.01 Memos to and from Traffic Operations Unit
453.02 Final Operational Report

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(460 - 492)

CATEGORY

RECORD TYPE

PHF
460 RIGHT OF WAY

461 Right of Way Correspondence 461.01 Memos to and from R/W Branch
462 Utilities Correspondence 462.01 Memos to and from Utilities Unit (including letters to utility companies)
463 Railroad/Utility Agreements 463.01 Agreements with utility companies, railroads, etc.
464 Utility Relocation Plans 464.01 Relocation plans for gas, power, etc.
465 Determination of Liability 465.01 Studies for utility/non-utility prior rights

X
466 Right of Way Contracts 466.01 Contracts, obligations, etc.
467 Right of Way Maps 467.01 Parcel, ownership, excess land, etc.
468 Cost Estimates 468.01 Fences, driveways, etc.
469 Resolution of Necessity 469.01 Resolution of Necessity data

X
470 SURVEYS

471 Surveys Correspondence 471.01 Memos to and from Surveys Unit
472 Survey Data 472.01 Aerial monuments, bench marks, etc.
480 TRAFFIC

481 Traffic Correspondence 481.01 Memos to and from Traffic Unit
482 Traffic Forecasts 482.01 Present/design year ADT, peak hour, etc.

X
483 Warrants 483.01 Signal warrants, median barrier warrants, lighting warrants, etc.

X
490 MEMOS TO FILE (INTRA-DISTRICT)

491 Phone Call Documentation 491.01 Phone call documentation
491.09 Phone call documentation affecting project decisions

X
492 Informal Meetings/Discussions 492.01 Notes of informal meetings
492.09 Notes affecting project decisions

X


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(500 - 524)

CATEGORY

RECORD TYPE

PHF
500 CONTRACT PREPARATION

510 PLANS

511 Basic Plans 511.01 Contour mapping, skeletons, contour grading, interchanges, intersections, profiles, superelevations, etc.
512 Drainage 512.01 Drainage plans, profiles, structure list, etc.
513 Traffic 513.01 Signing, Pavement Delineation Plan, electrical plans
513.09 Approval of Pavement Delineation Plan

X
514 Traffic Handling 514.01 Staging and detour plans, traffic control, etc.
515 Fencing 515.01 Types & locations, gates, etc.
516 Erosion Control 516.01 Plans with erosion control details and locations
517 Structures Plans 517.01 Final Structure Plans
518 Landscape Plans 518.01 Landscape Plans
519 Special Details 519.01 Construction notes, pavement markers, survey monuments, etc.
520 CALCULATIONS

521 Quantities 521.01 Checked contract items calculations
522 Earthwork Computations 522.01 EDP printouts or quantity sheets
522.02 Terrain Lists
522.03 Template Notes
522.04 Staking Notes, superelevations, etc.
523 Traverses 523.01 Computer printouts
524 Profiles 524.01 EDP printouts or grade sheet


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(530 - 538)

CATEGORY

RECORD TYPE

PHF
530 PS&E PROCESSING

531 PS&E Report 531.01 Report or Transmittal to Office Engineer for district or HQ

X
531.02 Liquidated damage calculations
532 Preliminary Estimate of Cost 532.01 BEES printout, bid price justification, segregations, etc.
532.02 Final Engineers Estimate

X
533 Special Provisions 533.01 Specifications
534 Dummy 534.01 Proof special provisions, transmittal letters, etc.
534.02 Addenda
535 Request for Funds 535.01 Request and Justification

X
535.02 FNM-76 Approval

X
536 CTC Vote of Funds 536.01 Fund authorization by CTC

X
537 Resident Engineer Information 537.01 Copies of working data for Resident Engineer


PROJECT DEVELOPMENT UNIFORM FILE SYSTEM
(600 - 622)

CATEGORY

RECORD TYPE

PHF
600 PROJECT MISCELLANEOUS

610 SPECIAL STUDIES

611 Bicycle 611.01 Completed studies and/or reports

X
612 Park and Ride 612.01 Completed studies and/or reports

X
613 Bus Loading Facilities 613.01 Completed studies and/or reports

X
614 Resource Conservation 614.01 Completed studies and/or reports

X
615 Value Analysis 615.01 Completed studies and/or reports

X
616 Hazardous Waste 616.01 Completed studies and/or reports

X
617 HOV Report 617.01 Completed studies and/or reports

X
620 PROJECT SAFETY

621 Safety Analysis 621.01 Completed studies and/or reports

X
622 Design for Safety Recommendations 622.01 Recommendations, memos, etc.

X
622.02 Decision documents, memos

X
623 Safety Reviews 623.01 Safety reviews and/or reports

X
630 PHOTOGRAPHS

631 Project Photos 631.01 Preconstruction photos

X
632 Special Photos 632.01 Accidents, storm damage, etc.

X



 Table of Contents

 Expanded Table of Contents

  Index

 PDPM Home Page 

 Design Home Page


For questions or feedback concerning this web site email: ranjeet.bagha@dot.ca.gov

This web site last modified July 1, 1999.


This web site last modified August 12, 1997.

Go to Top of Document