Inquiry #1: Can you please provide a cut sheet or specification for the electronic marker cast inside a pull box. Thank you
Inquiry submitted 01/18/2013

Response #1:Pending
Response posted 01/23/2013


Response #2:Please bid as you see it.
Response posted 01/23/2013




Inquiry #2: Traffic charts, Chart 2 is for East Lake Forest Dr., Traffic control can be sued during the day shift. For west Lake Forest Dr, can we utilize chart 2 or do we need to use chart 3, which is only for the night hours or weekends?
Inquiry submitted 01/28/2013

Response #1:Please bid as you see it and note that Chart 3 can only be used during median/new lane construction as stated under 'Remarks'.
Response posted 01/28/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.