Inquiry #1: Specifications section 10-1.14 Pumping Plant Equipment indicates the contractor as part of Total Pumping and Maintenence Requirements will clean among other items the "Storage Bays". Per plans these bays occur under the freeway for locations 1, 2, 3, seperate from the pump station itself. No information is present in the plans or specifications that detail the dimensions and or how much dirt, debris, sand, sediments are existing in the Storage Bays. With the cleaning and maintenance requirements in the specifications the contractor may be required to clean the bays multiple times. Without a clear understanding as to the volume a price would be impossible to provide.

Please provide a clear scope of work at the "storage bays" and or include a bid item for such work.

Inquiry submitted 11/28/2012

Response #1:Submitted for consideration.

Response posted 11/29/2012


Response #2:Please refer to Addendum #1

Response posted 12/05/2012




Inquiry #2: Contract documents require the bidder to provide alternate pumping facilites during the work that will provide equal capacity to the existing systems.

Please provide the total capacity for each station.

Inquiry submitted 11/28/2012

Response #1:Submitted for consideration.

Response posted 11/29/2012


Response #2:Please refer to sheets M1-2, M2-2, M3-2, and M4-1 for the capacity of the existing pumps.
Response posted 11/30/2012




Inquiry #3: We would like to request the possibility of a second bid date extension, Please.
Inquiry submitted 12/17/2012

Response #1:Submitted for consideration.
Response posted 12/17/2012


Response #2:Please bid per the current contract documents.
Response posted 12/17/2012


Response #3:Please refer to Addendum #3.


Response posted 12/19/2012




Inquiry #4: Requesting bid postponement until after holiday, we are having trouble getting an Elec Subs to bid project on Dec 20th. This is highly specialized work, we have relationships with good Elec Subs that do this work all the time but they need more time, and there is only one Elec Sub who has pulled plans and they need more time for their take-off.
Inquiry submitted 12/19/2012

Response #1:Submitted for consideration.
Response posted 12/19/2012


Response #2:Please refer to Addendum #3.


Response posted 12/19/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.