Inquiry #1: This project is only allowing for 20 Working Days. I think this project will take at least 35 Working Days to complete with Installing Signs, Installing SWPPP items, installing Rumble Strips, Removing Pavement Markings, Installing the Chip Seal, and Installing the new Striping/Markers.

Please change to at least 35 Working Days.


Inquiry submitted 10/25/2012

Response #1:Submitted for consideration.
Response posted 10/25/2012


Response #2:
Response posted 10/25/2012


Response #3:Working days are short, but reasonable, please bid accordingly.
Response posted 10/30/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.