Caltrans Office Engineer

Viewing inquiries for 08-0Q9204

Submit new inquiry for this project


Inquiry #1: I can't find the acceptable hours of operation for the (3) locations. If I overlooked them, I apologize.

Inquiry submitted 05/07/2013

Response #1:Submitted for consideration.
Response posted 05/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.