Viewing inquiries for 08-0C2104
Submit new inquiry for this projectInquiry #1: (1) will we be able to keep the continious lane closure (detour) per sheet DE-1 for the 15 working days of the project
(2) will survey and testing be provided by CalTrans
Inquiry submitted 12/18/2012
Response #1:Submitted for cosiderations
Response posted 12/18/2012
Response #2:(1)Refer to Page 42. A complete closure will only be allowed from 6AM Mondays to 6AM Wednesdays.
(2)What type of land survey is being referenced? There are several types of testing that may be provided by Caltrans. Please be more specific as to what type of testing.
Response posted 12/19/2012
Inquiry #2: (1) what line item do we carry the backfill after the concrete is placed
Inquiry submitted 12/18/2012
Response #1:Submitted for consideration
Response posted 12/18/2012
Response #2:36" Corrugated Steel Pipe, per page 515 of the 2006 Standard Specifications.
Response posted 12/19/2012
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.