Inquiry #1: Per section 4 Beginning of Work, Time of Completion and Liquidated Damages, the contractor shall start work on the 15th day after contract approval. Our concern and question is: This does not give us enough time to procure the truss and sign panels to start and complete the project within 60 working days, could more time be added for procurement?

Inquiry submitted 12/12/2012

Response #1:Please bid per contract documents.
Response posted 12/12/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.