Inquiry #1: Is this project re-bid
Inquiry submitted 09/24/2012

Response #1:This project is now readvertising. Responses to any previous inquiries have been incorporated into the revised contract documents.
Response posted 09/25/2012




Inquiry #2: Per 10-1.36 Staining Galvanized MBGR Railing Surfaces, paragragh #3 indicates that this is now going to be a field application? Please claify.
Inquiry submitted 09/28/2012

Response #1:Submitted for consideration.
Response posted 10/01/2012


Response #2:Statement #3 does not indicate that this work is going to be a field application only. It requires the contractor to submit proposed methods to protect adjacent surfaces around the MBGR components and gives the contractor the option to perform the staining off-site or on-site.
Response posted 10/04/2012




Inquiry #3: WHEN WILL ADDENDUM 3 DATED 10/12/12 BE AVAILABLE TO DOWNLOAD?

Inquiry submitted 10/15/2012

Response #1:Addendum No. 1 dated October 12, 2012 is now available for download.
Response posted 10/15/2012




Inquiry #4: Are the new steel posts for the reconstruct metal beam guardrail to be stained as well?
Inquiry submitted 10/17/2012

Response #1:Submitted for consideration.
Response posted 10/17/2012


Response #2:Yes. Reference Contract Special Provision, section 10-1.36 STAINING GALVANIZED METAL BEAM GUARD RAILING SURFACES, and section 10-1.19 EXISTING HIGHWAY FACILITIES, “RECONSTRUCT METAL BEAM GUARD RAILING".

Response posted 10/18/2012




Inquiry #5: Will this project be awarded if the responsible low bid exceeds the Engineer's estimate by more than 25%? That estimate + 25% appears to be in the range of $1,800,000 X 125% = $ 2,250,000.
Inquiry submitted 10/17/2012

Response #1:After all bids are opened, the State will analyze the bids to determine whether to recommend award to the apparent low bidder or not. The analysis will include and not be limited to supporting documents, bid balance, contingency allocation, other funding, competition, and the final review of contract plans and specifications.
Response posted 10/22/2012




Inquiry #6: 1-Same question as was posted previously as #4- Will galvn. steel components of Reconstructed MBGR require " Staining of Galvanized Surfaces"?

2-Who is responsible for requiring all excess cost, and why has the department continued to spend highway safety improvement funds (this project titled as " MBGR Reconstruction") by issuing contract documents that require " Staining of Galvanized Surfaces"? Is this stain a new safety feature? Will this requirement be deleted by addendum before the bid date?


Inquiry submitted 10/17/2012

Response #1:1) For Item No. 17, Reconstruct Metal Beam Guard Railing.
Existing Metal Beam Guard Railing elements, existing end cap (Type C), and hardware (bolts and nuts) will not be stained; only the new steel posts require staining.

2) Staining of Galvanized Surfaces Special Provision is part of the bid as presented to the bidders. This staining is not a new Safety feature. Per this posting, this requirement will not be deleted by addendum before the bid date(tomorrow).
Response posted 10/22/2012




Inquiry #7: Please clarify if your " estimated cost of the project" is $1,800,000 as shown on page 1 of the special provisions, or is it $ 1,600,000 as shown on the web site for advertised projects.
Inquiry submitted 10/17/2012

Response #1:Refer to Addendum No. 2, dated October 22, 2012.
Response posted 10/22/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.