Submit new inquiry for this projectInquiry #1: The bid quantity for Timber Lagging,Bid Item #72, is given on the bid form as 189MBF. The quantity for the Timber Lagging shown for Wall #1 (on sheet #93 of the plans)is 83MBF, which seems accurate.
Based on our take off, the quantity for the Timber Lagging at Wall #2 (shown on sheet #111 of the plans as 106MBF) seems low by about 7MBF. We come up with 113.8MBF of Timber Lagging for Wall #2.
Can you please confirm that there is only 106MBF of Timber Lagging on Wall #2?
Thank you.
Inquiry submitted 10/30/2012
Response #1:10/30/12: Your inquiry has been received and is being reviewed. Thank you for your patience.
Response posted 10/30/2012
Response #2: 11/2/12: Your inquiry is being reviewed. Until an addendum is issued addressing your concern, please bid per the current contract bid documents.
Response posted 11/02/2012
Response #3:11/13/12: Please refer to Addendum Number 1. The information is posted at http://www.dot.ca.gov/hq/esc/oe/project_ads_addenda/01/01-423704/ad1
Response posted 11/13/2012
Inquiry #2: Section 10-1.01 says that vegetation and tree removal shall be confined to the period September 14 to January 31. Is this correct?
Inquiry submitted 11/09/2012
Response #1:11/13/12: Your inquiry is under review. Please note that due to the current time frame between the inquiry submittal and the bid opening date, a response may not be provided before the bid opening. If a response is not provided before the bid opening addressing your concern, please bid per the current contract documents. Thank you for your patience.
Response posted 11/13/2012
Response #2:11/13/12: The dates are correct. Please bid per contract documents.
Response posted 11/13/2012
Inquiry #3: Item 59 tack coat estimated quantity shows 39 tons please clarify quantity
Inquiry submitted 11/13/2012
Response #1:11/14/12: Your inquiry is under review. Please note that due to the current time frame between the inquiry submittal and the bid opening date, a response may not be provided before the bid opening. If a response is not provided before the bid opening addressing your concern, please bid per the current contract documents. Thank you for your patience.
Response posted 11/14/2012
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.