Viewing inquiries for 11-408504

Submit new inquiry for this project


Inquiry #1: Addendum No.1 has an updated bid sheet but the contract number on the new sheet is 07-1W6104.
Inquiry submitted 05/16/2014

Response #1:At the bidder's request this inquiry has been rescinded. See bidders inquiry #2
Response posted 05/16/2014




Inquiry #2: Ignore last request. My mistake. Thank you and sorry.
Inquiry submitted 05/16/2014

Response #1:See bidders inquiry #1.
Response posted 05/16/2014




Inquiry #3: Where the plans call for Shrub Removal (Oleanders) do the shrubs need to be removed entirely including the rootball?
Inquiry submitted 05/23/2014

Response #1:Refer to section 20-1.03C(2) of the RSS for section 20 dated 11-15-13.
Response posted 05/23/2014






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.