Viewing inquiries for 06-0Q6304

Submit new inquiry for this project


Inquiry #1: We would like to request that Caltrans grant more working days for this project. Example, contract #06-0G6104 is similar in the type of work and has 70 working days and half as much work as this project.
We request that Caltrans change the working days for this project to 140 working days.

Inquiry submitted 03/14/2017

Response #1:Submitted for consideration.
Response posted 03/14/2017


Response #2:Refer to Addendum No. 1, dated March 16, 2017.
Response posted 03/21/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.