Inquiry #1: Contract specifies Rubberized Hot Mix Asphalt (Gap Graded) in Item #12. RHMA may not readily available especially with such a small qty. Will the State entertain using a more readily availabel mix?

Inquiry submitted 06/11/2013

Response #1:Submitted for consideration.
Response posted 06/11/2013


Response #2:No, please bid using current contract requirements.
Response posted 06/13/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.