Viewing inquiries for 04-4A5104

Submit new inquiry for this project


Inquiry #1: Hinges at the following locations have interference with the existing storage building: A2-80, A2-83, E5-83. At these locations temporary supports & falsework conflict with the existing storage units.
Please provide the following:
1. Access Agreements & timing with the storage units owners.
2. Location of falsework & temporary supports so it does not conflict with the storage operation & access.
Without appropriate & timely response we cannot design the temporary supports & falsework. Your prompt response is requested.

Inquiry submitted 09/13/2013

Response #1:Submitted for consideration.
Response posted 09/16/2013




Inquiry #2: We had previously submitted a bidder's inquiry to get some clarification regarding this contract & was told that a third addendum would be issued regarding these questions. The bid date is now two weeks away & still no addendum. Two weeks is insufficient time to design a falsework system & estimate the job properly. We reguest that when an addendum is issued it will include a bid date postponement.
Inquiry submitted 10/30/2013

Response #1:Submitted for consideration.
Response posted 10/31/2013




Inquiry #3: Special Provision Add to section 15-4.01C(2)(a) discusses removal of the pipe seat extenders and cable restrainers in relation to the "holiday weekend road closure". Section 12 restricts road closures on holiday weekends. Please clarify this conflict.
Inquiry submitted 11/22/2013

Response #1:Submitted for consideration.
Response posted 11/22/2013


Response #2:The"Lane Closure Restriction for Designated Holidays and Special Days" table in section 12-4.04 restricts closures on designated holidays, excluding Memorial Day, Independence Day, and Labor Day. In other words, closures are not restricted on these three holiday weekends. Please refer to the legend at the bottom of the table. Also, see Addendum 3.
Response posted 11/26/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.