Right Column
Project Description
Work will begin on this $1.17 Million project beginning November 27, 2007. The project will repair and resurface the bridge decks of the NB I-15 to the WB SR-91 connector and the bridges over Temescal Wash. Improvements include replacing the joint seal assemblies on the NB I-15 to the WB SR-91 Connector.
Work is scheduled at night, Monday through Friday, from 8 PM to 5AM (with weekend work as needed). East and westbound 91, along with north and southbound I-15, will be affected by the project. At times, full closures of the connectors are required to complete this project. Expect lanes closures and traffic control. Stay informed and prepare for your commute by having an alternate route selected.
Closure / Detour Maps
Northbound I-15 to Westbound SR-91 Connector
Southbound I-15 to Westbbound SR-91 Connector
Eastbound SR-91 to Northbound and Southbound I-15 Connectors