California Department of Transportation
 

Contract 06-446704

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) The special provisions state to place additional RHMA-G along the pavement edge to construct conforms to road connections and private drives. Per the plans, the road connections as well as the private drive connections show using HMA (Type A). Please specify which material is to be used at the intersecting road conforms and the private drive conforms?

A1) Please refer to Addendum No. 1 dated August 13, 2010. 28Sep10.


Q2) If HMA is the required material for either the road or private drive conforms, will a temporay taper be required along the intersecting pavements until the HMA can be placed?

A2) Please refer to Addendum No. 1 dated August 13, 2010. 28Sep10.


Q3) If a temporary taper is required, will the temporary taper need to be the width of a travel lane or the entire length of "L1 & L2" shown on Q-4?

A3) Please refer to Addendum No. 1 dated August 13, 2010. 28Sep10.


Q4) Under section 10-1.16, "Crack Treatment", Is it a typing error or do you want a 1.5 inch crack filled with hot melt. This wold be contradictory to paragraph one under construction where you dictate that "repair cracks wider than 0ne inch as ordered." which is the detail you are going to require?

A4) No further information is available at this time. Please bid per the contract documents. 28Sep10.