The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) As per the Special Provisions page 108, section 4. The number of working days ( 50 ) is very aggresive and unreasonable to perform the amount of work under this contract. Adding working days ( up to 15-20 ) should be considered.

A) The number of working days will remain the same, please bid it accordingly.

Please see addendum 1 issued 4-11-07.


Q2) The number of working days ( 50 ) is a very aggressive schedule due to the square meters to be ground plus the other work that is associated with this project. A new contract has been advertised on Route 41 ( 06-0c6604 ) that includes 66500 M2 of Grind Existing Pcc with 30 working days and longer working hours.

A) Please see addendum 1 issued 4-11-07.


Q3) Caltrans consideration to add working days will increase competetion and not limit the amount of Bidders on this project.

A) Please see addendum 1 issued 4-11-07.