The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Need an estimate of fees relating to getting permit regarding stormwater control since work involves digging through asphalt, concrete and dirt to lay electrical lines for solar panels.

A1) Contractor is responsible for all fees and permits required to complete the work. 18Mar10


Q2) Whom should we contact for clarification on whether we need to go through this stormwater control?

A2) Stormwater control mandates and references are covered within the contract documents. Please bid accordingly. 22Mar10.


Q3) Xxxxx?

A3) Xxxxx.