California Department of Transportation
 

Contract 05-0S1804

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Plan sheet C-1, Construction Details, currently shows the installation of Rubberized Hot Mix Asphalt (Gap Graded) on the intersections and driveways off of Hwy 41. Would Caltrans consider to install HMA Type A as an alternative at those locations? The intersections and driveways would require hand work with the HMA placement, as currenly shown. However, the hand work could be a problem with Rubberized HMA placement with its elastic properties.

A1) Please bid in accordance with the current contract plans and documents. 10Mar10


Q2) Xxxxx?

A2) Xxxxx.


Q3) Xxxxx?

A3) Xxxxx.